  • Question
  • A can write 32 pages in 6 hours and B can write 40 pages in 5 hours. If they write together, in how many hours they can write 110 pages ?


  • Options
  • A. 7 hrs
  • B. 6 hrs 10 min
  • C. 5 hrs 25min
  • D. 8 hrs 15 min

  • Correct Answer
  • 8 hrs 15 min 

    Explanation

    A can write in 1hour = 32/6 pages

    Similarly, B in 1 hour = 40/5 pages

    Together (A+B) in 1 hour = 32/6 + 40/5 = 40/3

    So, A+B write 40/3 pages in 1 hour

    A+B write 110 pages in (3/40) x 110 Hours = 8 hours 15 min.

  • Tags: GATE, CAT, Bank Exams, AIEEE, Bank PO, Bank Clerk

    Time and Work problems


    Search Results


    • 1. A shopkeeper has a job to print certain number of documents and there are three machines P, Q and R for this job. P can complete the job in 3 days, Q can complete the job in 4 days and R can complete the job in 6 days. How many days the shopkeeper will it take to complete the job if all the machines are used simultaneously ?

    • Options
    • A. 4/3 days
    • B. 2 days
    • C. 3/2 days
    • D. 4 days
    • Discuss
    • 2. Ten women can do a work in six days. Six men can complete the same work in five days. What is the ratio between the capacity of a man and a woman?

    • Options
    • A. 1:2
    • B. 2:1
    • C. 2:3
    • D. 3:2
    • Discuss
    • 3. A and B together finish a wor in 20 days.They worked together for 15 days and then B left. Afer another 10 days,A finished the remaining work. In how many days A alone can finish the job?

    • Options
    • A. 30
    • B. 40
    • C. 50
    • D. 60
    • Discuss
    • 4. S, T and U together can complete a work in 30 days. If the ratio of efficiency of S, T and U is 20 : 15 : 12 respectively, then in how many days U alone can complete the same work?

    • Options
    • A. 195/2
    • B. 235/2
    • C. 225/2
    • D. 215/2
    • Discuss
    • 5. P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work together ?

    • Options
    • A. 5 (2/3)
    • B. 6 (3/4 )
    • C. 4 (1/2)
    • D. 3
    • Discuss
    • 6. A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --- days ?

    • Options
    • A. 51/24
    • B. 87/5
    • C. 57/12
    • D. 60/11
    • Discuss
    • 7. A take twice as much time as B or thrice as much time to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in ?

    • Options
    • A. 3 hrs
    • B. 6 hrs
    • C. 7 hrs
    • D. 5 hrs
    • Discuss
    • 8. A work which could be finished in 11 days was finished 4 days earlier after 4 more men joined. The number of men employed was ?

    • Options
    • A. 7
    • B. 8
    • C. 9
    • D. 10
    • Discuss
    • 9. A laborer is engaged for 30 days on the condition that he receives Rs.25 for each day he works and is fined Rs.7.50 for each day is absent. He gets Rs.425 in all. For how many days was he absent ?

    • Options
    • A. 10 days
    • B. 14 days
    • C. 11 days
    • D. 9 days
    • Discuss
    • 10. Sixty men can stitch 150 shirts in 30 days working 8 hours a day. In how many days can 35 men stitch 200 shirts working 6 hours a day ?

    • Options
    • A. 87.5
    • B. 89
    • C. 91.5
    • D. 93.5
    • Discuss