logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • If 34 men completed 2/5th of a work in 8 days working 9 hours a day. How many more man should be engaged to finish the rest of the work in 6 days working 9 hours a day ?


  • Options
  • A. 101 men
  • B. 112 men
  • C. 102 men
  • D. 120 men

  • Correct Answer
  • 102 men 

    Explanation

    From the above formula i.e (m1 x t1/w1) = (m2 x t2/w2)

    so, [(34 x 8 x 9)/(2/5)] = [(M x 6 x 9)/(3/5)]

    so, M = 136 men

     

    Number of men to be added to finish the work = 136-34 = 102 men.

  • Tags: GATE, CAT, Bank Exams, AIEEE, Bank PO, Bank Clerk

    Time and Work problems


    Search Results


    • 1. 45 men working 9 hours per day dig 40 m deep. How many extra men should be put to dig to a depth of 56 m working 7 hours per day ?

    • Options
    • A. 36
    • B. 61
    • C. 48
    • D. 54
    • Discuss
    • 2. If 5 men and 2 boys working together, can do four times as much work per hour as a man and a boy together. Find the ratio of the work done by a man and that of a boy for a given time ?

    • Options
    • A. 1:2
    • B. 1:3
    • C. 3:1
    • D. 2:1
    • Discuss
    • 3. P and Q were assigned to do a work for an amount of 1200. P alone can do it in 15 days while Q can do it in 12 days. With the help of R they finish the work in 6 days. Find the share of R ?

    • Options
    • A. 120
    • B. 240
    • C. 360
    • D. 180
    • Discuss
    • 4. A group of men can complete a job in K hours. After every 4 hours, half the number of men working at that point of time leave the job. Continuing this way if the job is finished in 16 hours, what is the value of K ?

    • Options
    • A. 7 hrs
    • B. 7.5 hrs
    • C. 8 hrs
    • D. 8.25 hrs
    • Discuss
    • 5. A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?

    • Options
    • A. [7 + (215/345)] days
    • B. [6 + (11/215)] days
    • C. [6 + (261/315)] days
    • D. [5 + (112/351)] days
    • Discuss
    • 6. P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work together ?

    • Options
    • A. 5 (2/3)
    • B. 6 (3/4 )
    • C. 4 (1/2)
    • D. 3
    • Discuss
    • 7. S, T and U together can complete a work in 30 days. If the ratio of efficiency of S, T and U is 20 : 15 : 12 respectively, then in how many days U alone can complete the same work?

    • Options
    • A. 195/2
    • B. 235/2
    • C. 225/2
    • D. 215/2
    • Discuss
    • 8. A and B together finish a wor in 20 days.They worked together for 15 days and then B left. Afer another 10 days,A finished the remaining work. In how many days A alone can finish the job?

    • Options
    • A. 30
    • B. 40
    • C. 50
    • D. 60
    • Discuss
    • 9. Ten women can do a work in six days. Six men can complete the same work in five days. What is the ratio between the capacity of a man and a woman?

    • Options
    • A. 1:2
    • B. 2:1
    • C. 2:3
    • D. 3:2
    • Discuss
    • 10. A shopkeeper has a job to print certain number of documents and there are three machines P, Q and R for this job. P can complete the job in 3 days, Q can complete the job in 4 days and R can complete the job in 6 days. How many days the shopkeeper will it take to complete the job if all the machines are used simultaneously ?

    • Options
    • A. 4/3 days
    • B. 2 days
    • C. 3/2 days
    • D. 4 days
    • Discuss


    Comments

    There are no comments.

Enter a new Comment