After day 1, A finishes 1/9 of the work.
After day 2, B finishes 1/7 more of the total work. (1/9) + (1/7) is finished.
After day 3, C finishes 1/5 more of total work. Total finished is 143/315.
So, after day 6, total work finished is 286/315.
Now remaining work = 29 /315
On day 7, A will work again
Work will be completed on day 7 when A is working. He must finish 29/315 of total remaining work.
Since he takes 9 days to finish the total task, he will need 261/315 of the day.
Total days required is 6 + (261/315) days.
0.0169 / 0.0130 = 169 / 130
= 13 / 10
Given Exp. = 4 / 7 + {(2q - p) / (2q + p)}
Dividing numerator as well as denominator by q,
Exp = 4/7 + {2-p/q) / (2 + p/q)}
= 4/7 + {(2 - 4/5) / (2 + 4/5)}
= 4/7 + 6/14
= 4/7 + 3/7
=7/7
=1.
25% of 25% = (25/100) x (25/100) = 625/10000 = 0.625
Let y% of 20 = .05
Then, (y x 20)/100 = .05
? y = .25
2 | 24 - 36 - 40 -------------------- 2 | 12 - 18 - 20 -------------------- 2 | 6 - 9 - 10 ------------------- 3 | 3 - 9 - 5 ------------------- | 1 - 3 - 5 L.C.M. = 2 x 2 x 2 x 3 x 3 x 5 = 360.
81/3% = (25/3 x 1/100) = 1/12
.025 = (25/1000) x 100% = 2.5%
Let N% of 2/7 is 1/35
? (2/7 x N) / 100 = 1/35
? N = 1/35 x 7/2 x 100 = 10%
Let the money interest at 8% interest be ? P .
Then, the money interest at 10% interest = ?(4000 - P)
According to the question,
(P x 8 x 1)/100 + [(4000 - P) x 10 x 1]/100 = 352
? 8P + 40000 - 10P = 35200
? 40000 - 35200 = 2P
? P = 4800/2 = ? 2400
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.