Total Water reqduired = 5000 × 150 lit = 750,000 litres = 750 cu.m.
Volume of tank = 20 × 15 × 5 = 1500 Cu.m.
Number of days required =1500/750 = 2 days.
Ratio of efficiencies of P, Q and R = 2 : 3 : 4
From the given data,
Number of working days of P, Q, R = 5 : 10 : 5
Hence, ratio of amount of p, Q, R = 2x5 : 3x10 : 4x5 = 10 : 30 : 20
Amounts of P, Q, R = 200, 600 and 400.
Given Lasya can do a work in 16 days.
Time taken by Rashmi = n days
=> (12 x 20)/(20 - 12) = (12 x 20)/n
=> n= 30 days.
Required ratio of efficiencies of Rashmi and Lasya = 1/30 :: 1/16 = 8 : 15.
Total work is given by L.C.M of 72, 48, 36
Total work = 144 units
Efficieny of A = 144/72 = 2 units/day
Efficieny of B = 144/48 = 3 units/day
Efficieny of C = 144/36 = 4 units/day
According to the given data,
2 x p/2 + 3 x p/2 + 2 x (p+6)/3 + 3 x (p+6)/3 + 4 x (p+6)/3 = 144 x (100 - 125/3) x 1/100
3p + 4.5p + 2p + 3p + 4p = 84 x 3 - 54
p = 198/16.5
p = 12 days.
Now, efficency of D = (144 x 125/3 x 1/100)/10 = 6 unit/day
(C+D) in p days = (4 + 6) x 12 = 120 unit
Remained part of work = (144-120)/144 = 1/6.
4/10 + 9/x = 1 => x = 15
Then both can do in
1/10 + 1/15 = 1/6 => 6 days
Since 20% i.e 1/5 typists left the job. So, there can be any value which is multiple of 5 i.e, whose 20% is always an integer. Hence, 5 is the least possible value.
Let work done by 1 man in i day be m
and Let work done by 1 boy in 1 day be b
From the given data,
4(5m + 3b) = 23
20m + 12b = 23....(1)
2(3m + 2b) = 7
6m + 4b = 7 ....(2)
By solving (1) & (2), we get
m = 1, b = 1/4
Let the number of required boys = n
6(7 1 + n x 1/4) = 45
=> n = 2.
Raghu can complete the work in (12 x 9)hrs = 108 hrs.
Arun can complete the work in (8 x 11)hrs = 88 hrs.
Raghu's 1 hrs work = 1/108 and Arun's 1 hrs work = 1/88
(Raghu + Arun)'s 1 hrs work =
So, both Raghu and Arun will finish the work in
Number of days of 12 hours each= =
Given Prabhas is twice as good a workman as Rana.
Prabhas finishes the work in 3 hrs
=> Rana finishes the work in 6 hrs.
Number of hours required together they could finish the work
= 3 x 6 / 3 + 6
= 18/9
= 2 hrs.
Let number of days Charan can do the same work alone is 'd' days.
According to the given data,
Therefore, Charan alone can complete the work in 96 days.
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.