logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • Three taps P, Q and R can fill a tank in 12 hrs, 15 hrs and 20 hrs respectively. If P is open all the time and Q and R are open for one hour each alternately, starting with Q, then the tank will be full in how many hours ?


  • Options
  • A. 9 hrs
  • B. 7 hrs
  • C. 13 hrs
  • D. 11 hrs

  • Correct Answer
  • 7 hrs 

    Explanation

    Given,

    P can fill in 12 hrs

    Q can fill in 15 hrs

    R can fill in 20 hrs

    => Volume of tank = LCM of 12, 15, 20 = 60 lit

    => P alone can fill the tank in 60/12 = 5 hrs

    => Q alone can fill the tank in 60/15 = 4 hrs

    => R alone can fill the tank in 60/20 = 3 hrs

    Tank can be filled in the way that

    (P+Q) + (P+R) + (P+Q) + (P+R) + ....

    => Tank filled in 2 hrs = (5+4) + (5+3) = 9 + 8 = 17 lit

    => In 6 hrs = 17 x 6/2 = 51 lit

    => In 7th hr = 51 + (5+4) = 51 + 9 = 60 lit

    => So, total tank will be filled in 7 hrs.

  • Tags: AIEEE, Bank Exams, CAT, GATE, Bank Clerk, Bank PO

    Time and Work problems


    Search Results


    • 1. Kaushalya can do a work in 20 days, while kaikeyi can do the same work in 25 days. They started the work jointly.Few days later Sumitra also joined them and thus all of them completed the whole work in 10 days. All of them were paid total Rs.700. What is the Share of Sumitra?

    • Options
    • A. Rs.130
    • B. Rs.185
    • C. Rs.70
    • D. can't be determined
    • Discuss
    • 2. Priya can do a work in 16 days. In how many days will the work be completed by Sai, if the efficiency of Sai is 60% more than that of Priya ?

    • Options
    • A. 8 days
    • B. 12 days
    • C. 14 days
    • D. 10 days
    • Discuss
    • 3. Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual efficiency and Sravan with his normal efficiency then the work is completed in 20 days. How many days would it take if Sravan alone works with his actual efficiency (in Days)?

    • Options
    • A. 50
    • B. 100
    • C. 70
    • D. 35
    • Discuss
    • 4. After working for 8 days, Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ?

    • Options
    • A. 24 1/2 days
    • B. 25 3/2 days
    • C. 24 2/3 days
    • D. 26 2/3 days
    • Discuss
    • 5. 6 boys and 8 girls can do job in 10 days , 26 boys & 48 women do work in 2 days. Find time taken by 15 boys and 20 girls to do same work ?

    • Options
    • A. 2 days
    • B. 3 days
    • C. 4 days
    • D. 5 days
    • Discuss
    • 6. P and Q can do a work in 4 hours and 12 hours respectively. P starts the work at 9am and they work alternately for one hour each. When will the work be completed ?

    • Options
    • A. 3 am
    • B. 12 pm
    • C. 1 pm
    • D. 3 pm
    • Discuss
    • 7. K can lay Highway road between two cities in 16 days. L can do the same job in 12 days. With the help of M, they completes the job in 4 days. How much days does it take for M alone to complete the work ?

    • Options
    • A. 47/7 days
    • B. 59/6 days
    • C. 48/5 days
    • D. 57/5 days
    • Discuss
    • 8. P, Q, and R can do a job in 12 days together. If their efficiency of working be in the ratio 3 : 8 : 5, Find in what time Q can complete the same work alone?

    • Options
    • A. 36 days
    • B. 30 days
    • C. 24 days
    • D. 22 days
    • Discuss
    • 9. 5 boys and 3 girls can together cultivate a 23 acre field in 4 days and 3 boys and 2 girls together can cultivate a 7 acre field in 2 days. How many girls will be needed together with 7 boys, if they cultivate 45 acres of field in 6 days?

    • Options
    • A. 4
    • B. 3
    • C. 2
    • D. 1
    • Discuss
    • 10. Meghana alone would take 32 hours more to complete a job than both Meghana and Ganesh together. If Ganesh worked alone, he took 12 1/2 hours more to complete it than both Meghana and Ganesh worked together. What time would they take if both Meghana and Ganesh worked together?

    • Options
    • A. 20 hrs
    • B. 18 hrs
    • C. 22 hrs
    • D. 20.5 hrs
    • Discuss


    Comments

    There are no comments.

Enter a new Comment