We know that Time is inversely proportional to Efficiency
Here given time ratio of P & P+Q as
P/P+Q = 150/100 = 3:2
Efficiency ratio of P & Q as
P:Q = 2:1 ....(1)
Given Efficiency ratio of Q & R as
Q:R = 3:1 ....(2)
From (1) & (2), we get
P:Q:R = 6:3:1
P alone can finish the work in
22.5(3+1)/6 = 15 days.
47/10000 = .0047
.02 =(2/100) x 100% =2%
Let N / 11 = 233
Then, N = 233 x 11 = 2563
? Missing digit is 5.
121012 = 12 x 10084 + 4
? remainder = 4
We have the important relation, More work, More time (days)
? A piece of work can be done in 6 days.
? Three times of work of same type can be done in 6 x 3
= 18 days
? = 750.0003 ÷ 19.999
? ? ? 750 ÷ 20
? ? ? 375 ? 38
Subtract 20, 25, 30, 35, 40, 45 from successive numbers. So 0 is wrong.