logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?


  • Options
  • A. 24.5 days
  • B. 26.6 days
  • C. 25 days
  • D. 20 days

  • Correct Answer
  • 26.6 days 

    Explanation

    Arun has completed 1 3 rd of the work in 8 days

    Then he can complete the total work in

    1 3  ---- 8

     1 ---- ?

    = 24 days


    But given Akhil is only 60% as efficient as Arun

    Akhil = 1 24 × 60 100 = 1 40

    Akhil can complete the total work in 40 days

    Now, remaining 2/3rd of work can be completed in

     1  ------   40

    2 3  ------   ?  

    = 26.66 days.

  • Tags: CAT, Bank Exams, Bank PO, Bank Clerk

    Time and Work problems


    Search Results


    • 1. P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?

    • Options
    • A. 56 days
    • B. 54 days
    • C. 60 days
    • D. 64 days
    • Discuss
    • 2. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days what is time taken by 15 men and 20 boys?

    • Options
    • A. 4 days
    • B. 6 days
    • C. 7 days
    • D. 5 days
    • Discuss
    • 3. P alone can do a piece of work in 24 days. The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work. How many days are required to complete by P and Q working together ?

    • Options
    • A. 9 3/5 days
    • B. 7 days
    • C. 6 3/7 days
    • D. 8 days
    • Discuss
    • 4. Amit can do a piece of work in 45 days, but Bharath can do the same work in 5 days less, than Amit, when working alone. Amit and Bharath both started the work together but Bharath left after some days and Amit finished the remaining work in 56 days with half of his efficiency but he did the work with Bharath with his complete efficiency. For how many days they had worked together?

    • Options
    • A. 6
    • B. 8
    • C. 9
    • D. 12
    • Discuss
    • 5. A can do a piece of work in 30 days. He works at it for 6 days and then B finishes it in 18 days. In what time can A and B together it ?

    • Options
    • A. 14 1/2 days
    • B. 11 days
    • C. 13 1/4 days
    • D. 12 6/7 days
    • Discuss
    • 6. If 10 men take 15 days to complete a work. In how many days will 37 men complete the work?

    • Options
    • A. 3 days
    • B. 4 days
    • C. 5 days
    • D. 6 days
    • Discuss
    • 7. 6 men can complete a piece of work in 12 days. 8 women can complete the same piece of work in 18 days whereas 18 children can complete the piece of work in 10 days. 4 men, 12 women and 20 children work together for 2 days. If only men were to complete the remaining work in 1 day how many men would be required totally?

    • Options
    • A. 38
    • B. 72
    • C. 36
    • D. 76
    • Discuss
    • 8. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it ?

    • Options
    • A. 40 days
    • B. 36 days
    • C. 32 days
    • D. 34 days
    • Discuss
    • 9. 12 men complete a work in 9 days. After they have worked for 6 days, 4 more men join them. How many days will they take to complete the remaining work ?

    • Options
    • A. 2 days
    • B. 2.5 days
    • C. 2.25 days
    • D. 3 days
    • Discuss
    • 10. M can complete a piece of work in 10 days. N is 33.33% less efficient than M. calculate the number of days required to both to complete the work?

    • Options
    • A. 6 days
    • B. 8 days
    • C. 11 days
    • D. 13 days
    • Discuss


    Comments

    There are no comments.

Enter a new Comment