Arun has completed rd of the work in 8 days
Then he can complete the total work in
---- 8
1 ---- ?
= 24 days
But given Akhil is only 60% as efficient as Arun
Akhil =
Akhil can complete the total work in 40 days
Now, remaining 2/3rd of work can be completed in
1 ------ 40
------ ?
= 26.66 days.
According to question ,we can say that
From equation ?. x4 = 398 + 227 = 625
? x4 = 54
From equation ?. y2 = 346 - 321 = 25
? y2 = 52
But, Feb 2004 not included because we are calculating from March 2004 to March 2005. So it has 1 odd day only.
∴ The day on 6th March, 2005 will be 1 day beyond the day on 6th March, 2004.
Given that, 6th March, 2005 is Monday.
∴ 6th March, 2004 is Sunday (1 day before to 6th March, 2005).
Couldn't be determined, since the total amount of money is not given in either of the case
Given that a /b = b/c
? b2 = ac
? a4 : b4 = a4 : a2 c2 = a2 : c2
Given, A = 6 km/h, B = 3 km/ h
According to the formula, Average speed = 2AB/(A + B)
? Required average speed = 2 x 6 x 3/(6 + 3)
= 36/9 = 4 km/h
Given that, W + D = 6 ...(i)
[ w = Time taken while walking and
D = Time taken while driving ]
From Eq. (i)
5 +D = 6
? D = 1
2D = 2 x 1 = 2
? He will take 2 h to drive both ways.
175760 = 24 x 5 x 13 3
= 23 x 2 x 5 x 133
To make perfect cube, it must be divided by 2 x 5 = 10
On comparing it with ax2 + bx + c = 0 , we get a = 1, b = p, c = q
The roots of the equation x2 + px + q = 0 are equal if
b2 - 4ac = 0
? p2 - 4q = 0 ? p2 = 4q.
Thus , required answer is option B .
Let the volume be x3 and 27x3
? Their edges are x and 3x
Now Ratio of their surface area = 6x2 : 54x2 = 1 : 9
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.