logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • A can finish a work in 18 days and B can do the same work in half the time taken by A. then, working together, what part of the same work they can finish in a day ?


  • Options
  • A. Total work
  • B. One-fourth work
  • C. Half work
  • D. Two-third work

  • Correct Answer
  • Half work 

    Explanation

    A can do the work = 18 days
    B can do the work = 18/2 = 9 days
    (A + B)'s 1 day work = 1/18 + 1/9 = 1/6
    => In 3 days = 3x1/6 = 1/2 work is completed.

  • Tags: AIEEE, Bank Exams, CAT, GATE, Bank Clerk, Bank PO

    Time and Work problems


    Search Results


    • 1. 10 men and 15 women together can complete a work in 6 days. It takes 100 days for one man alone to complete the same work. How many days will be required for one woman alone to complete the same work?

    • Options
    • A. 215 days
    • B. 225 days
    • C. 235 days
    • D. 240 days
    • Discuss
    • 2. If 2 men and 3 women can do a piece of work in 8 days and 3 men and 2 women in 7 days. In how many days can the work be done by 5 men and 4 women working together?

    • Options
    • A. 3 days
    • B. 6 days
    • C. 4 days
    • D. 2 days
    • Discuss
    • 3. A and B together can do a piece of work in 40 days. A having worked for 20 days, B finishes the remaining work alone in 60 days. In How many days shall B finish the whole work alone?

    • Options
    • A. 60
    • B. 70
    • C. 80
    • D. 90
    • Discuss
    • 4. 4 men can repair a road in 7 hours. How many men are required to repair the road in 2 hours ?

    • Options
    • A. 17 men
    • B. 14 men
    • C. 13 men
    • D. 16 men
    • Discuss
    • 5. When A, B and C are deployed for a task , A and B together do 70% of the work and B and C together do 50% of the work. who is most efficient?

    • Options
    • A. A
    • B. B
    • C. C
    • D. can't be determined
    • Discuss
    • 6. A can do a piece of work in 30 days. He works at it for 6 days and then B finishes it in 18 days. In what time can A and B together it ?

    • Options
    • A. 14 1/2 days
    • B. 11 days
    • C. 13 1/4 days
    • D. 12 6/7 days
    • Discuss
    • 7. Amit can do a piece of work in 45 days, but Bharath can do the same work in 5 days less, than Amit, when working alone. Amit and Bharath both started the work together but Bharath left after some days and Amit finished the remaining work in 56 days with half of his efficiency but he did the work with Bharath with his complete efficiency. For how many days they had worked together?

    • Options
    • A. 6
    • B. 8
    • C. 9
    • D. 12
    • Discuss
    • 8. P alone can do a piece of work in 24 days. The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work. How many days are required to complete by P and Q working together ?

    • Options
    • A. 9 3/5 days
    • B. 7 days
    • C. 6 3/7 days
    • D. 8 days
    • Discuss
    • 9. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days what is time taken by 15 men and 20 boys?

    • Options
    • A. 4 days
    • B. 6 days
    • C. 7 days
    • D. 5 days
    • Discuss
    • 10. P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?

    • Options
    • A. 56 days
    • B. 54 days
    • C. 60 days
    • D. 64 days
    • Discuss


    Comments

    There are no comments.

Enter a new Comment