Given that
(10M + 15W) x 6 days = 1M x 100 days
=> 60M + 90W = 100M
=> 40M = 90W
=> 4M = 9W.
From the given data,
1M can do the work in 100 days
=> 4M can do the same work in 100/4= 25 days.
=> 9W can do the same work in 25 days.
=> 1W can do the same work in 25 x 9 = 225 days.
Hence, 1 woman can do the same work in 225 days.
4th observation i.e., 8 is the median.
47/10000 = .0047
.02 =(2/100) x 100% =2%
Let N / 11 = 233
Then, N = 233 x 11 = 2563
? Missing digit is 5.
121012 = 12 x 10084 + 4
? remainder = 4
We have the important relation, More work, More time (days)
? A piece of work can be done in 6 days.
? Three times of work of same type can be done in 6 x 3
= 18 days
? = 750.0003 ÷ 19.999
? ? ? 750 ÷ 20
? ? ? 375 ? 38