  • Question
  • A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?


  • Options
  • A. 10 %
  • B. 14 ( 2/7 )%
  • C. 20 %
  • D. Can't be determined

  • Correct Answer
  • 14 ( 2/7 )% 

    Explanation

    Let he initially employed x workers which works for D days and he estimated 100 days for the whole work and then he doubled the worker for (100-D) days.

    D * x +(100- D) * 2x= 175x 

    =>  D= 25 days 

    Now , the work done in 25 days = 25x 

    Total work = 175x

    Therefore, workdone before increasing the no of workers =  25 x 175 x × 100  % =  14 2 7 %


  • Time and Work problems


    Search Results


    • 1. A works twice as fast as B.If B can complete a work in 18 days independently,the number of days in which A and B can together finish the work is:

    • Options
    • A. 4 days
    • B. 6 days
    • C. 8 days
    • D. 10 days
    • Discuss
    • 2. A can do a certain work in the same time in which B and C together can do it.If A and B together could do it in 20 days and C alone in 60 days ,then B alone could do it in:

    • Options
    • A. 20days
    • B. 40 days
    • C. 50 days
    • D. 60 days
    • Discuss
    • 3. A and B can do a piece of work in 30 days , while B and C can do the same work in 24 days and C and A in 20 days . They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

    • Options
    • A. 18 days
    • B. 24 days
    • C. 30 days
    • D. 36 days
    • Discuss
    • 4. P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they complete the work?

    • Options
    • A. 60/11
    • B. 61/11
    • C. 71/11
    • D. 72/11
    • Discuss
    • 5. 12 men can complete a work in 8 days. 16 women can complete the same work in 12 days. 8 men and 8 women started working and worked for 6 days. How many more men are to be added to complete the remaining work in 1 day?

    • Options
    • A. 8
    • B. 12
    • C. 16
    • D. 24
    • Discuss
    • 6. A,B,C together can do a piece of work in 10 days.All the three started workingat it together and after 4 days,A left.Then,B and C together completed the work in 10 more days.In how many days can complete a work alone ?

    • Options
    • A. 25
    • B. 24
    • C. 23
    • D. 21
    • Discuss
    • 7. The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is:

    • Options
    • A. 4.5
    • B. 5
    • C. 6
    • D. 9 1/3
    • Discuss
    • 8. A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in 55% of the time. How many workers were there in the group?

    • Options
    • A. 50
    • B. 40
    • C. 45
    • D. 10
    • Discuss
    • 9. (x-2) men can do a piece of work in x days and (x+7) men can do 75% of the same work in (x-10)days. Then in how many days can (x+10) men finish the work?

    • Options
    • A. 27 days
    • B. 12 days
    • C. 25 days
    • D. 18 days
    • Discuss
    • 10. An air conditioner can cool the hall in 40 miutes while another takes 45 minutes to cool under similar conditions. If both air conditioners are switched on at same instance then how long will it take to cool the room approximately ?

    • Options
    • A. 18 minutes
    • B. 19 minutes
    • C. 22 minutes
    • D. 24 minutes
    • Discuss


    Comments

    There are no comments.

Enter a new Comment