logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they complete the work?


  • Options
  • A. 60/11
  • B. 61/11
  • C. 71/11
  • D. 72/11

  • Correct Answer
  • 60/11 

    Explanation

    P can complete the work in (12 x 8) hrs = 96 hrs 

    Q can complete the work in (8 x 10) hrs=80 hrs 

    Therefore, P's 1 hour work=1/96   and Q's 1 hour work= 1/80

    (P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs  

    Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11


  • Time and Work problems


    Search Results


    • 1. 12 men can complete a work in 8 days. 16 women can complete the same work in 12 days. 8 men and 8 women started working and worked for 6 days. How many more men are to be added to complete the remaining work in 1 day?

    • Options
    • A. 8
    • B. 12
    • C. 16
    • D. 24
    • Discuss
    • 2. A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

    • Options
    • A. 11 days
    • B. 12 days
    • C. 13 days
    • D. 14 days
    • Discuss
    • 3. A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 3000 as wages for the whole work, what are the daily wages of A, B and C respectively (in Rs):

    • Options
    • A. 200, 250, 300
    • B. 300, 200, 250
    • C. 200, 300, 400
    • D. None of these
    • Discuss
    • 4. B starts 4 minutes after A from the same point, for a place at a distance of 7 miles from the starting point. A on reaching the destination turns back and walks a mile where he meets B. If A's speed is a mile in 8 minutes then B's speed is a mile in ____ minutes.

    • Options
    • A. 9
    • B. 12
    • C. 10
    • D. 8
    • Discuss
    • 5. Two cars A and B travel from one city to another, at speeds of 72 km/hr and 90 km/hr respectively. If car B takes 1 hour lesser than car A for the journey, then what is the distance (in km) between the two cities?

    • Options
    • A. 270
    • B. 360
    • C. 240
    • D. 400
    • Discuss
    • 6. A and B can do a piece of work in 30 days , while B and C can do the same work in 24 days and C and A in 20 days . They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

    • Options
    • A. 18 days
    • B. 24 days
    • C. 30 days
    • D. 36 days
    • Discuss
    • 7. A can do a certain work in the same time in which B and C together can do it.If A and B together could do it in 20 days and C alone in 60 days ,then B alone could do it in:

    • Options
    • A. 20days
    • B. 40 days
    • C. 50 days
    • D. 60 days
    • Discuss
    • 8. A works twice as fast as B.If B can complete a work in 18 days independently,the number of days in which A and B can together finish the work is:

    • Options
    • A. 4 days
    • B. 6 days
    • C. 8 days
    • D. 10 days
    • Discuss
    • 9. A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

    • Options
    • A. 10 %
    • B. 14 ( 2/7 )%
    • C. 20 %
    • D. Can't be determined
    • Discuss
    • 10. A,B,C together can do a piece of work in 10 days.All the three started workingat it together and after 4 days,A left.Then,B and C together completed the work in 10 more days.In how many days can complete a work alone ?

    • Options
    • A. 25
    • B. 24
    • C. 23
    • D. 21
    • Discuss


    Comments

    There are no comments.

Enter a new Comment