One day's work of A, B and C = (1/24 + 1/30 + 1/40) = 1/10.
C leaves 4 days before completion of the work, which means only A and B work during the last 4 days.
Work done by A and B together in the last 4 days = 4 (1/24 + 1/30) = 3/10.
Remaining Work = 7/10, which was done by A,B and C in the initial number of days.
Number of days required for this initial work = 7 days.
Thus, the total numbers of days required = 4 + 7 = 11 days.
A's 5 days work = 50%
B's 5 days work = 33.33%
C's 2 days work = 16.66% [100- (50+33.33)]
Ratio of contribution of work of A, B and C = = 3 : 2 : 1
A's total share = Rs. 1500
B's total share = Rs. 1000
C's total share = Rs. 500
A's one day's earning = Rs.300
B's one day's earning = Rs.200
C's one day's earning = Rs.250
1 man's 1 day work =1/96 ; 1 woman's 1 day work = 1/192
Work done in 6 days=
Remaining work = 1/4
(8 men +8 women)'s 1 day work = =1/8
Remaining work =1/4 - 1/8 = 1/8
1/96 work is done in 1 day by 1 man
Therefore, 1/8 work will be done in 1 day by 96 x (1/8) =12 men
P can complete the work in (12 x 8) hrs = 96 hrs
Q can complete the work in (8 x 10) hrs=80 hrs
Therefore, P's 1 hour work=1/96 and Q's 1 hour work= 1/80
(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs
Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11
2(A+B+C)'s 1 day work = 1/30 + 1/24 + 1/20 = 1/8
=>(A+B+C)'s 1 day's work= 1/16
work done by A,B and C in 10 days=10/16 = 5/8
Remaining work= 3/8
A's 1 day's work=
Now, 1/48 work is done by A in 1 day.
So, 3/8 work wil be done by A in =48 x (3/8) = 18 days
(A+B)'s 1 day's work=1/20
C's 1 day work=1/60
(A+B+C)'s 1 day's work= 1/20 + 1/60 = 1/15
Also A's 1 day's work =(B+C)'s 1 day's work
Therefore, we get: 2 x (A's 1 day 's work)=1/15
=>A's 1 day's work=1/30
Therefore, B's 1 day's work= 1/20 - 1/30 = 1/60
So, B alone could do the work in 60 days.
Ratio of rates of working of A and B =2:1. So, ratio of times taken =1:2
Therefore, A's 1 day's work=1/9
B's 1 day's work=1/18
(A+B)'s 1 day's work= 1/9 + 1/18 = 1/6
so, A and B together can finish the work in 6 days
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.