Given, SI1 - SI2 = 110,
T1 = 2 Yr,
T2 = 1 yr, R1 = 8%, R2 = 5%
According to the question,
[(P x 8 x 2)/100] - [(P x 5 x 1)/100] = 110
? 11P/100 = 110
? P = ? 1000
4th observation i.e., 8 is the median.
47/10000 = .0047
.02 =(2/100) x 100% =2%
Let N / 11 = 233
Then, N = 233 x 11 = 2563
? Missing digit is 5.
121012 = 12 x 10084 + 4
? remainder = 4
We have the important relation, More work, More time (days)
? A piece of work can be done in 6 days.
? Three times of work of same type can be done in 6 x 3
= 18 days
? = 750.0003 ÷ 19.999
? ? ? 750 ÷ 20
? ? ? 375 ? 38