CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Engineering Economy
Comments
Question
The owner of the construction company makes use of the estimate :
Options
A. to determine the capital investment costs.
B. to assist in financial arrangements
C. to determine economic feasibility of the project.
D. to determine the tax, insurance and evaluation purpose.
E. All of these
Correct Answer
All of these
Engineering Economy problems
Search Results
1. Keeping in view, the feasibility order of magnitude, the preliminary, conceptual or budget estimates, are prepared by :
Options
A. architect/engineer
B. construction manager
C. owner himself/herself
D. construction manager
E. None of these
Show Answer
Scratch Pad
Discuss
Correct Answer: owner himself/herself
2. A project construction cost estimate includes:
Options
A. the labour and material cost
B. the equipment and over head cost
C. the profit of the contractor
D. All of these
Show Answer
Scratch Pad
Discuss
Correct Answer: All of these
3. Pick up the correct statement from the following:
Options
A. Uniform series compound amount factor =
B. Uniform series present worth factor =
C. Sinking fund factor =
D. Capital recovery factor =
where letters carry their usual meanings.
E. All of these
Show Answer
Scratch Pad
Discuss
Correct Answer: All of these
4. Pick up the method used for project evaluation and selection in capital budgetting from the following:
Options
A. pay back period
B. Internal ratio of return
C. Net present worth
D. Profitability index
E. All the above
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above
5. Which one of the following is not a construction estimate?
Options
A. Initial feasibility estimate
B. Conceptual preliminary budget
C. Definite estimate
D. None of these
Show Answer
Scratch Pad
Discuss
Correct Answer: None of these
6. Pick up the correct statement from the following:
Options
A. The receipts and disbursements in a given time interval are referred to as cash flow.
B. The assumptions that all cash flows occur at the end of the interest period, is known as the end of period convention.
C. A cash flow diagram is a graphical representation of cash flows drawn on a time scale.
D. The cash flow diagram represents the statement of the problem and also includes what is given and what is to be found.
E. All of the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All of the above.
7. Pick up the correct statement from the following:
Options
A. The difference between sales revenue and cost of goods sold, is known as 'Gross Profit.'
B. The gross profit percentage is the average profit margin obtained on goods sold.
C. The relationship of contribution to sales is known as contribution ratio
D. The difference between sales and variable cost of sales, is called contribution.
E. All of these
Show Answer
Scratch Pad
Discuss
Correct Answer: All of these
8. Renu Bala deposits Rs 1200 now, Rs 800 two years from now and Rs 1000 five years from now. If the savings bank's rate of interest in 5%, she will receive an amount of Rs
X
10 years from now, where
X
is
Options
A. Rs 3415
B. Rs 4225
C. Rs 4413
D. Rs 4826
Show Answer
Scratch Pad
Discuss
Correct Answer: Rs 4413
9. If
P
is principal amount,
i
is the rate of interest per annum and
n
is the number of periods in years, the compound amount factor (CAF) is :
Options
A. (1 +
i
)
n
B. (1 +
i
)
(1/2
n
)
C.
(
n
+
i
)
D. None of these
Show Answer
Scratch Pad
Discuss
Correct Answer: (1 +
i
)
n
10. The construction manager uses the estimate of the project
Options
A. to tell the owner of the project to take his/her financial decision.
B. to advise the architect/engineer regarding design cost parameter especially in value engineering analysis.
C. to develop bids on the project.
D. to control the project during its construction.
E. All of these
Show Answer
Scratch Pad
Discuss
Correct Answer: All of these
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering