CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Highway Engineering
Comments
Question
Pick up the incorrect statement from the following. On highways circular curves may be
Options
A. simple curves
B. compound curves
C. reverse curves
D. vertical curves
E. all the above.
Correct Answer
vertical curves
Highway Engineering problems
Search Results
1. The length of a transition curve, is governed by
Options
A. rate of change of radial acceleration
B. rate of change of super-elevation
C. both (a) and (b)
D. neither (a) nor (b)
Show Answer
Scratch Pad
Discuss
Correct Answer: both (a) and (b)
2. The ratio of maximum deviation angle and maximum polar deflection angle of a Lemniscate curve, is
Options
A. 2
B. 3
C. 4
D. 5
E. 6
Show Answer
Scratch Pad
Discuss
Correct Answer: 3
3. Ruling gradient on hill roads 300 m above M.S.L. is kept
Options
A. 4%
B. 5%
C. 6%
D. 7%
E. 8%
Show Answer
Scratch Pad
Discuss
Correct Answer: 5%
4. In complex situations, total time required for a driver to form a judgement and to act, may be taken as
Options
A. 1.0 sec
B. 1.5 sec
C. 2.0 sec
D. 2.5 sec
E. 3.0 sec
Show Answer
Scratch Pad
Discuss
Correct Answer: 3.0 sec
5. Roadway width for a National highways and State highways (two-lanes) is
Options
A. 12 m
B. 9 m
C. 9.5 m
D. 15 m
Show Answer
Scratch Pad
Discuss
Correct Answer: 12 m
6. The minimum cross fall of shoulders is kept
Options
A. 0.5%
B. 1.0%
C. 1.5%
D. 2.5%
E. 3%
Show Answer
Scratch Pad
Discuss
Correct Answer: 3%
7. Thickness of broken centre line markings for a four lane road, is generally kept
Options
A. 10 cm
B. 12 cm
C. 15 cm
D. 18 cm
E. 20 cm
Show Answer
Scratch Pad
Discuss
Correct Answer: 15 cm
8. In welded wire mesh, the longitudinal wire is placed at
Options
A. 10 cm centres
B. 15 cm centres
C. 20 cm centres
D. 25 cm centres
E. 30 cm centres
Show Answer
Scratch Pad
Discuss
Correct Answer: 15 cm centres
9. Along a hill road, a side drain is provided on
Options
A. outer side of a spur curve
B. outer side of a re-entrant curve
C. outer side of both (
a
) and (
b
)
D. inner side of both (
a
) and (
b
)
Show Answer
Scratch Pad
Discuss
Correct Answer: inner side of both (
a
) and (
b
)
10. Pick up the correct statement from the following:
Options
A. Borrow pits are located out side the right of way
B. Borrow pits may be located on either side of the right of way
C. Spoil bank is located on one side of the right of way
D. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering