CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Concrete Technology
Comments
Question
Pick up the correct statement from the following:
Options
A. Construction joints in columns are provided a few cm below the junction of beam
B. Construction joints in columns are provided at the bottom haunching
C. Construction joints in beams and slabs are provided within middel third
D. Constructionjoints are generally provided in positions subjected to least shear force
E. All the above.
Correct Answer
All the above.
Concrete Technology problems
Search Results
1. Inert material of a cement concrete mix, is
Options
A. water
B. cement
C. aggregate
D. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: aggregate
2. The strength and quality of concrete, depend upon:
Options
A. grading of aggregates
B. surface area of aggregates
C. shape of aggregates
D. surface texture of aggregates
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
3. Pick up the correct statement from the following:
Options
A. There should not be any loss of cement from the charged drum of the mixer
B. Cement should be mixed for at least one minute
C. 10% of water is placed in the rotating drum before adding dry material
D. 10% of water is added after placing the other ingredients in the drum
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
4. If 50 kg of fine aggregates and 100 kg of coarse agregates are mixed in a concrete whose water cement ratio is 0.6, the weight of water required for harsh mix, is
Options
A. 8 kg
B. 10 kg
C. 12 kg
D. 14 kg
E. 15 kg.
Show Answer
Scratch Pad
Discuss
Correct Answer: 12 kg
5. Pick up the incorrect statement from the following:
Options
A. Space between the exterior walls of a warechouse and bag piles should be 30 cm
B. Cement bags should preferably be piled on wooden planks
C. Cement bags should be placed such that bags of one layer does not touch the bags of the adjacent layer
D. Width and height of the pile should not exceed 3 m and 2.70 m respectively
E. None of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: None of these.
6. Horizontal construction joints in concrete walls are generally provided at
Options
A. soffit level
B. window sill level
C. floor level
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
7. An excess of flaky particles in concrete aggregates
Options
A. decreases the workability
B. increases the quantity of water and sand
C. affects the durability of concrete
D. more than 15% are not desirable
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
8. An aggregate is known as cyclopean aggregate if its size is more than
Options
A. 4.75 mm
B. 30 mm
C. 60 mm
D. 75 mm
E. 90 mm.
Show Answer
Scratch Pad
Discuss
Correct Answer: 75 mm
9. In the method of voids for determination of the quantity of cement paste, it is assumed that
Options
A. Voids in coarse aggregates are filled by fine aggregates
B. Voids in fine aggregates are filled by the cement paste
C. Volume of fine aggregates is equal to total voids in coarse aggregates plus 10% extra
D. Volume of cement paste required is equal to total volume of voids in fine aggregates plus 15% extra
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
10. Curing of pavements, floors, roofs and slabs, is done by
Options
A. membrane method
B. ponding method
C. covering surface with bags
D. sprinkling water method
E. shading concrete method.
Show Answer
Scratch Pad
Discuss
Correct Answer: ponding method
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering