  • Batching error means inaccuracy in the quantity of


  • Options
  • A. aggregates
  • B. cement
  • C. water
  • D. all the above.

  • Correct Answer
  • all the above. 


  • Concrete Technology problems


    Search Results


    • 1. Hardening of cement occurs at

    • Options
    • A. rapid rate during the first few days and afterwards it continues to increase at a decreased rate
    • B. slow rate during the first few days and afterwards it continues to increase at a rapid rate
    • C. uniform rate throughout its age
    • D. none of these.
    • Discuss
    • 2. A construction joint is provided where

    • Options
    • A. bending moment is small
    • B. shear force is small
    • C. the member is supported by other member
    • D. all the above.
    • Discuss
    • 3. Pick up the correct statement from the following:

    • Options
    • A. Construction joints are necessarily planned for their locations
    • B. Expansion joints are provided to accommodate thermal expansion
    • C. Construction joints are provided to control shrinkage cracks
    • D. Expansion joints need not be provided in foundation concrete
    • E. All the above.
    • Discuss
    • 4. ISI has specified full strength of concrete after

    • Options
    • A. 7 days
    • B. 14 days
    • C. 21 days
    • D. 28 days
    • E. none of these.
    • Discuss
    • 5. For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are:

    • Options
    • A. 70 litres of sand and 120 litres of aggregates
    • B. 70 kg of sand and 140 litres of aggregates
    • C. 105 litres of sand and 140 litres of aggregates
    • D. 105 litres of sand and 210 litres of aggregates
    • E. none of these.
    • Discuss
    • 6. The maximum thickness of concrete floor of a cement warehouse, is

    • Options
    • A. 10 cm
    • B. 15 cm
    • C. 20 cm
    • D. 25 cm
    • E. 30 cm
    • Discuss
    • 7. Addition of pozzolana to cement causes

    • Options
    • A. reduction in permeability
    • B. loss of heat of hydration
    • C. reduction in bleeding
    • D. increase in curing time
    • E. all the above.
    • Discuss
    • 8. Pick up the correct statement from the following:

    • Options
    • A. Water cement paste hardens due to hydration
    • B. During hardening cement binds the aggregates together
    • C. Cement provides strength, durability and water tightness to the concrete
    • D. All the above.
    • Discuss
    • 9. Too wet concrete may cause

    • Options
    • A. weakness of concrete
    • B. excessive laitance
    • C. segregation
    • D. lower density
    • E. all the above.
    • Discuss
    • 10. Pick up the correct statement from the following:

    • Options
    • A. Lime in excess, causes the cement to expand and disintegrate
    • B. Silica in excess, causes the cement to set slowly
    • C. Alumina in excess, reduces the strength of the cement
    • D. Magnesium oxide in excess, remains in free state and makes the cement unsound