  • A construction joint is provided where


  • Options
  • A. bending moment is small
  • B. shear force is small
  • C. the member is supported by other member
  • D. all the above.

  • Correct Answer
  • all the above. 


  • Concrete Technology problems


    Search Results


    • 1. Pick up the correct statement from the following:

    • Options
    • A. Construction joints are necessarily planned for their locations
    • B. Expansion joints are provided to accommodate thermal expansion
    • C. Construction joints are provided to control shrinkage cracks
    • D. Expansion joints need not be provided in foundation concrete
    • E. All the above.
    • Discuss
    • 2. ISI has specified full strength of concrete after

    • Options
    • A. 7 days
    • B. 14 days
    • C. 21 days
    • D. 28 days
    • E. none of these.
    • Discuss
    • 3. For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are:

    • Options
    • A. 70 litres of sand and 120 litres of aggregates
    • B. 70 kg of sand and 140 litres of aggregates
    • C. 105 litres of sand and 140 litres of aggregates
    • D. 105 litres of sand and 210 litres of aggregates
    • E. none of these.
    • Discuss
    • 4. Addition of pozzolana to ordinary port land cement, causes

    • Options
    • A. decrease in early strength
    • B. reduction in chemical action with sulphates
    • C. increase in shrinkage
    • D. reduction bleeding
    • E. all the above.
    • Discuss
    • 5. Water required per bag of cement, is

    • Options
    • A. 7 kg
    • B. 14 kg
    • C. 21 kg
    • D. 28 kg
    • E. 35 kg
    • Discuss
    • 6. Hardening of cement occurs at

    • Options
    • A. rapid rate during the first few days and afterwards it continues to increase at a decreased rate
    • B. slow rate during the first few days and afterwards it continues to increase at a rapid rate
    • C. uniform rate throughout its age
    • D. none of these.
    • Discuss
    • 7. Batching error means inaccuracy in the quantity of

    • Options
    • A. aggregates
    • B. cement
    • C. water
    • D. all the above.
    • Discuss
    • 8. The maximum thickness of concrete floor of a cement warehouse, is

    • Options
    • A. 10 cm
    • B. 15 cm
    • C. 20 cm
    • D. 25 cm
    • E. 30 cm
    • Discuss
    • 9. Addition of pozzolana to cement causes

    • Options
    • A. reduction in permeability
    • B. loss of heat of hydration
    • C. reduction in bleeding
    • D. increase in curing time
    • E. all the above.
    • Discuss
    • 10. Pick up the correct statement from the following:

    • Options
    • A. Water cement paste hardens due to hydration
    • B. During hardening cement binds the aggregates together
    • C. Cement provides strength, durability and water tightness to the concrete
    • D. All the above.
    • Discuss