CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Building Construction
Comments
Question
The form work from the slabs excluding props, can be removed only after
Options
A. 1 day
B. 4 days
C. 7 days
D. 14 days
Correct Answer
4 days
Building Construction problems
Search Results
1. Which of the following metal sheets is most effective in preventing dampness?
Options
A. Copper sheets
B. lead sheets
C. aluminium sheets
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
2. An arch may fail due to
Options
A. uneven settlement of abutments
B. sliding of voussoirs
C. crushing of the material
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
3. For plastering the exposed brick walls, the cement sand mortar should be
Options
A. 1:2
B. 1:3
C. 1:4
D. 1:6
E. 1:8.
Show Answer
Scratch Pad
Discuss
Correct Answer: 1:4
4. The type of pointing in which upper side of mortar joints is kept about 12 mm inside the face of the masonry and bottom is kept flushed with face of wall, is
Options
A. truck pointing
B. recessed pointing
C. struck pointing
D. grooved pointing.
Show Answer
Scratch Pad
Discuss
Correct Answer: struck pointing
5. Pick up the correct statement from the following :
Options
A. Cavity of a cavity wall should start near ground level
B. Cavity of a cavity wall should terminate near eaves level of sloping roof
C. Cavity of a cavity wall should terminate near coping of flat roof with parapet wall
D. Damp proof course for two leaves of a cavity wall, is laid separately but at the same level
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
6. In soft clay of low bearing capacity, the type of steel pile generally used, is
Options
A. H-pile
B. screw pile
C. disc pile
D. pipe pile
E. raking pile.
Show Answer
Scratch Pad
Discuss
Correct Answer: screw pile
7. The sound which continues even after its source is cut off, is called
Options
A. reverberation
B. echo
C. intensity of sound
D. interference.
Show Answer
Scratch Pad
Discuss
Correct Answer: reverberation
8. The pile provided with one or more bulles in its vertical shaft, is generally known as
Options
A. under-ream pile
B. friction pile
C. bearing pile
D. sheet pile.
Show Answer
Scratch Pad
Discuss
Correct Answer: under-ream pile
9. The steel pile which is generally sunk in soft clay or loose sand of low bearing capacity, is
Options
A. H-pile
B. pipe pile
C. screw pile
D. disc pile
E. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: screw pile
10. The form work from the sides of beams can be removed only after
Options
A. 1 day
B. 4 days
C. 7 days
D. 14 days.
Show Answer
Scratch Pad
Discuss
Correct Answer: 1 day
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering