CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Building Construction
Comments
Question
The columns of multi-storeyed buildings are designed to withstand the forces due to
Options
A. dead loads
B. live loads
C. wind loads
D. earthquakes
E. all of these.
Correct Answer
all of these.
Building Construction problems
Search Results
1. The inclined surface of an abutment to receive the arch, is known as
Options
A. skew back
B. soffit
C. spandril
D. haunch.
Show Answer
Scratch Pad
Discuss
Correct Answer: skew back
2. In clay soil
Options
A. swelling and shrinkage characteristics prevail
B. consolidation continues even after several years of construction.
C. differential settlement is generally prevalent
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
3. The maximum permissible differential settlement, in case of foundations in clayey soil, is usually limited to
Options
A. 10 mm
B. 20 mm
C. 30 mm
D. 40 mm
E. 50 mm.
Show Answer
Scratch Pad
Discuss
Correct Answer: 40 mm
4. The black cotton soil
Options
A. undergoes volumetric changes
B. swells excessively when wet
C. shrinks excessively when dry
D. has a tendency of swelling and shrinking due to clay particles
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
5. Dampness causes
Options
A. efflorescence
B. bleaching of paints
C. crumbling of plaster
D. growth of termites
E. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: growth of termites
6. For brick construction, the lime-sand mortar, is
Options
A. 1:1
B. 1:2
C. 1:3
D. 1:4
E. 1:5.
Show Answer
Scratch Pad
Discuss
Correct Answer: 1:2
7. A floor constructed with 3 mm marble chips, is known
Options
A. mosaic floor
B. terrazo floor
C. chips floor
D. marble floor.
Show Answer
Scratch Pad
Discuss
Correct Answer: terrazo floor
8. The angle between skew back of a flat arch and the horizontal, is kept approximately equal to
Options
A. 0°
B. 30°
C. 60°
D. 90°
E. 120°.
Show Answer
Scratch Pad
Discuss
Correct Answer: 60°
9. For heavy embankments and dams, of height
h
, the depth of exploration of soil should not be less than
Options
A.
h
/4
B. 1/2
h
C.
h
D. 2
h
.
Show Answer
Scratch Pad
Discuss
Correct Answer: 2
h
.
10. Raft foundation are generally preferred to when the area required for individual footing, is more than
Options
A. 25% to total area
B. 30% of total area
C. 40% to total area
D. 50% of total area.
Show Answer
Scratch Pad
Discuss
Correct Answer: 50% of total area.
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering