logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Estimating and Costing Comments

  • Question
  • The slope of the oultet of 'P trap' below the horizontal is kept


  • Options
  • A. 8°
  • B. 10°
  • C. 12°
  • D. 14°

  • Correct Answer
  • 14° 


  • Estimating and Costing problems


    Search Results


    • 1. The measurement is made in square metre in case of

    • Options
    • A. Cement concrete in foundation
    • B. R.C.C. structure
    • C. Hollow concrete block wall
    • D. Concrete fencing posts
    • E. None of these.
    • Discuss
    • 2. The following item of earth work is not measured separately.

    • Options
    • A. Setting out of works
    • B. Site clearence
    • C. dead men
    • D. Steps in deep exavaction
    • E. All the above.
    • Discuss
    • 3. The floor area includes the area of the balcony up to

    • Options
    • A. 100%
    • B. 75%
    • C. 50%
    • D. 25%
    • Discuss
    • 4. The brick work is not measured in cu m in case of

    • Options
    • A. One or more than one brick wall
    • B. Brick work in arches
    • C. Reinforced brick work
    • D. Half brick wall.
    • Discuss
    • 5. Carpet area does not include the area of

    • Options
    • A. the walls along with doors and other openings
    • B. verandah, corridor and passage
    • C. bath room and lavatory
    • D. kitchen and pantry
    • E. All the above.
    • Discuss
    • 6. Pick up the correct statement from the following:

    • Options
    • A. In order to check up the average depth of excavation, 'Dead mans' are left at the mid-widths of borrow pits
    • B. The earthwork calculation in excavation is made from the difference in levels obtained with a level
    • C. The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
    • D. All the above.
    • Discuss
    • 7. The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is

    • Options
    • A. Rs. 400
    • B. Rs. 425
    • C. Rs. 450
    • D. Rs. 500
    • Discuss
    • 8. The value of 'B' of Indian type W.C. shown in the given figure is :

    • Options
    • A. 45 cm
    • B. 50 cm
    • C. 30 cm
    • D. 25 cm
    • Discuss
    • 9. Pick up the incorrect statement from the following:

    • Options
    • A. Lead is the average horizontal straight distance between the borrow pit and the place of spreading soil
    • B. The lead is calculated for each block of the excavated area
    • C. The unit of lead is 50 m for a distance upto 500 m
    • D. The unit of lead is 1 km where the lead exceeds 2 km.
    • Discuss
    • 10. The expected out turn for earth work in excavation in ordinary soil per mazdoor per day is

    • Options
    • A. 1.00 cum
    • B. 2.00 cum
    • C. 3.00 cum
    • D. 4.00 cum
    • Discuss


    Comments

    There are no comments.

Enter a new Comment