  • Question
  • The floor area includes the area of the balcony up to


  • Options
  • A. 100%
  • B. 75%
  • C. 50%
  • D. 25%

  • Correct Answer
  • 50% 


  • Estimating and Costing problems


    Search Results


    • 1. The brick work is not measured in cu m in case of

    • Options
    • A. One or more than one brick wall
    • B. Brick work in arches
    • C. Reinforced brick work
    • D. Half brick wall.
    • Discuss
    • 2. Carpet area does not include the area of

    • Options
    • A. the walls along with doors and other openings
    • B. verandah, corridor and passage
    • C. bath room and lavatory
    • D. kitchen and pantry
    • E. All the above.
    • Discuss
    • 3. The value of 'A' of Indian type W.C. shown in the given figure is :

    • Options
    • A. 25 cm
    • B. 30 cm
    • C. 40 cm
    • D. 45 cm
    • Discuss
    • 4. The expected out turn of half brick partition wall per mason per day is

    • Options
    • A. 1.5 m3
    • B. 2.0 m3
    • C. 4.0 m2
    • D. 5.0 m2
    • Discuss
    • 5. Pick up the correct statement from the following:

    • Options
    • A. Bricks are paid per thousand
    • B. Cement is paid per 50 kg bag
    • C. Lime is paid per quintal
    • D. Brick aggregates is paid per cum
    • E. All the above.
    • Discuss
    • 6. The following item of earth work is not measured separately.

    • Options
    • A. Setting out of works
    • B. Site clearence
    • C. dead men
    • D. Steps in deep exavaction
    • E. All the above.
    • Discuss
    • 7. The measurement is made in square metre in case of

    • Options
    • A. Cement concrete in foundation
    • B. R.C.C. structure
    • C. Hollow concrete block wall
    • D. Concrete fencing posts
    • E. None of these.
    • Discuss
    • 8. The slope of the oultet of 'P trap' below the horizontal is kept

    • Options
    • A. 8°
    • B. 10°
    • C. 12°
    • D. 14°
    • Discuss
    • 9. Pick up the correct statement from the following:

    • Options
    • A. In order to check up the average depth of excavation, 'Dead mans' are left at the mid-widths of borrow pits
    • B. The earthwork calculation in excavation is made from the difference in levels obtained with a level
    • C. The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
    • D. All the above.
    • Discuss
    • 10. The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is

    • Options
    • A. Rs. 400
    • B. Rs. 425
    • C. Rs. 450
    • D. Rs. 500
    • Discuss