CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Estimating and Costing
Comments
Question
Carpet area does not include the area of
Options
A. the walls along with doors and other openings
B. verandah, corridor and passage
C. bath room and lavatory
D. kitchen and pantry
E. All the above.
Correct Answer
All the above.
Estimating and Costing problems
Search Results
1. The value of '
A
' of Indian type W.C. shown in the given figure is :
Options
A. 25 cm
B. 30 cm
C. 40 cm
D. 45 cm
Show Answer
Scratch Pad
Discuss
Correct Answer: 30 cm
2. The expected out turn of half brick partition wall per mason per day is
Options
A. 1.5 m
3
B. 2.0 m
3
C. 4.0 m
2
D. 5.0 m
2
Show Answer
Scratch Pad
Discuss
Correct Answer: 2.0 m
3
3. Pick up the correct statement from the following:
Options
A. Bricks are paid per thousand
B. Cement is paid per 50 kg bag
C. Lime is paid per quintal
D. Brick aggregates is paid per cum
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
4. The trap which is provided to disconnect the house drain from the street sewer is called
Options
A. Master trap
B. Intercepting trap
C. Interception manhole
D. Intercepterchamber
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
5. Pick up the correct statement from the following:
Options
A. The incidental expenses of a miscellaneous character which could not be predicted during preparation of the estimate, is called contingencies
B. Additional supervising staff engaged at work site, is called work charged establishment
C. Detailed specifications specify qualities, quantities and the proportions of materials to be used for a particular item
D. The cost per unit at which the article can be procured, from the open market at a given time, is called 'market rate'
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
6. The brick work is not measured in cu m in case of
Options
A. One or more than one brick wall
B. Brick work in arches
C. Reinforced brick work
D. Half brick wall.
Show Answer
Scratch Pad
Discuss
Correct Answer: Half brick wall.
7. The floor area includes the area of the balcony up to
Options
A. 100%
B. 75%
C. 50%
D. 25%
Show Answer
Scratch Pad
Discuss
Correct Answer: 50%
8. The following item of earth work is not measured separately.
Options
A. Setting out of works
B. Site clearence
C. dead men
D. Steps in deep exavaction
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
9. The measurement is made in square metre in case of
Options
A. Cement concrete in foundation
B. R.C.C. structure
C. Hollow concrete block wall
D. Concrete fencing posts
E. None of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: None of these.
10. The slope of the oultet of '
P
trap' below the horizontal is kept
Options
A. 8°
B. 10°
C. 12°
D. 14°
Show Answer
Scratch Pad
Discuss
Correct Answer: 14°
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering