  • The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is


  • Options
  • A. 3250 m3
  • B. 3225 m3
  • C. 3275 m3
  • D. 3300 m3

  • Correct Answer
  • 3225 m3 


  • Estimating and Costing problems


    Search Results


    • 1. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

    • Options
    • A. 0.90 m3
    • B. 0.94 m3
    • C. 0.98 m3
    • D. 1.00 m3
    • Discuss
    • 2. The measurement is made for stone work in square metre in case of

    • Options
    • A. Wall facing
    • B. Columns, lintels, copings
    • C. Building work
    • D. Dressed stones in Chajjas
    • E. (a) and (d) of the above.
    • Discuss
    • 3. The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended

    • Options
    • A. 100 mm
    • B. 150 mm
    • C. 200 mm
    • D. 175 mm
    • Discuss
    • 4. Pick up the correct statement regarding the centre line method of estimating a building

    • Options
    • A. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
    • B. The centre line is worked out separately for different sections of walls of a building
    • C. The centre line length is reduced by half the layer of main wall joining the partition wall
    • D. All the above.
    • Discuss
    • 5. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds

    • Options
    • A. 2.0%
    • B. 2.5%
    • C. 4.0%
    • D. 5.0%
    • Discuss
    • 6. Pick up the correct statement from the following:

    • Options
    • A. Pointing is measured in sq.m
    • B. Plastering is measured in sq.m
    • C. Glazing is measured in sq.m
    • D. Striking is measured in sq.m
    • E. All the above.
    • Discuss
    • 7. Berms are provided in canals if these are

    • Options
    • A. fully in excavation
    • B. partly in excavtion and partly in embankment
    • C. fully in embankment
    • D. All the above.
    • Discuss
    • 8. According to Indian Standards Institute, the actual size of modular bricks is

    • Options
    • A. 23 cm x 11.5 cm x 7.5 cm
    • B. 25 cm x 13 cm x 7.5 cm
    • C. 19 cm x 9 cm x 9 cm
    • D. 20 cm x 10 cm x 10 cm
    • Discuss
    • 9. The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

    • Options
    • A. 1.00 m3
    • B. 1.25 m3
    • C. 1.50 m3
    • D. 1.75 m3
    • Discuss
    • 10. Pick up the incorrect statement from the following:

    • Options
    • A. The built up covered area at the floor level of any storey of a building is called plinth area
    • B. The usable covered area of the rooms of any storey of a building is called carpet area
    • C. The carpet area of a building along with area of its kitchen, pantry, store, lavatory, bath room and glazed verandah, is called floor area
    • D. None of these.
    • Discuss