  • The measurement is made for stone work in square metre in case of


  • Options
  • A. Wall facing
  • B. Columns, lintels, copings
  • C. Building work
  • D. Dressed stones in Chajjas
  • E. (a) and (d) of the above.

  • Correct Answer
  • (a) and (d) of the above. 


  • Estimating and Costing problems


    Search Results


    • 1. The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended

    • Options
    • A. 100 mm
    • B. 150 mm
    • C. 200 mm
    • D. 175 mm
    • Discuss
    • 2. Pick up the correct statement regarding the centre line method of estimating a building

    • Options
    • A. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
    • B. The centre line is worked out separately for different sections of walls of a building
    • C. The centre line length is reduced by half the layer of main wall joining the partition wall
    • D. All the above.
    • Discuss
    • 3. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds

    • Options
    • A. 2.0%
    • B. 2.5%
    • C. 4.0%
    • D. 5.0%
    • Discuss
    • 4. Size, capacity and materials need be specified for

    • Options
    • A. Bib-cocks
    • B. Stop-cocks
    • C. Ferrules
    • D. Ball valves
    • E. All the above.
    • Discuss
    • 5. Referring of given figure, pick up the correct statement from the following:

    • Options
    • A. The total length of centre line of four walls is 20 m
    • B. Length of long wall out-to-out is 6.80 m
    • C. Length of short walls in-to-in is 3.20 m
    • D. All the above.
    • Discuss
    • 6. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

    • Options
    • A. 0.90 m3
    • B. 0.94 m3
    • C. 0.98 m3
    • D. 1.00 m3
    • Discuss
    • 7. The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is

    • Options
    • A. 3250 m3
    • B. 3225 m3
    • C. 3275 m3
    • D. 3300 m3
    • Discuss
    • 8. Pick up the correct statement from the following:

    • Options
    • A. Pointing is measured in sq.m
    • B. Plastering is measured in sq.m
    • C. Glazing is measured in sq.m
    • D. Striking is measured in sq.m
    • E. All the above.
    • Discuss
    • 9. Berms are provided in canals if these are

    • Options
    • A. fully in excavation
    • B. partly in excavtion and partly in embankment
    • C. fully in embankment
    • D. All the above.
    • Discuss
    • 10. According to Indian Standards Institute, the actual size of modular bricks is

    • Options
    • A. 23 cm x 11.5 cm x 7.5 cm
    • B. 25 cm x 13 cm x 7.5 cm
    • C. 19 cm x 9 cm x 9 cm
    • D. 20 cm x 10 cm x 10 cm
    • Discuss