C. sequence of various activities is made according to their importance
D. net work is drawn by connecting the activities and the events
E. All the above.
Correct Answer
All the above.
Construction Management problems
Search Results
1. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is