logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Construction Management Comments

  • Question
  • Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
    Optimistic time, most likely time and pessimistic times for the activities of a network in the given


  • Options
  • A. 20
  • B. 25
  • C. 35
  • D. 15

  • Correct Answer
  • 25 


  • Construction Management problems


    Search Results


    • 1. For the network shown in the given figure, the expected time for the activity

    • Options
    • A. 1-2 is 4
    • B. 2-3 is 7
    • C. 3-4 is 8
    • D. all the above.
    • Discuss
    • 2. Pick up the incorrect statement from the following:

    • Options
    • A. The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
    • B. The difference between the maximum time available for the job and actual time it consumes, is called total float
    • C. The difference between the latest start time and earliest start time of an activity, is called total float
    • D. The difference between the earliest finish time of an activity and the earliest start time of its successor activity, is called free float of the activity
    • E. None of these.
    • Discuss
    • 3. The final selection of a construction site, is done by

    • Options
    • A. departmental representative or user
    • B. local civil authority representative
    • C. representative of engineer authority
    • D. representative of administration
    • E. all the above.
    • Discuss
    • 4. For the execution of a project, a contractor is

    • Options
    • A. a person
    • B. a firm
    • C. an agency
    • D. all the above.
    • Discuss
    • 5. Which one of the following represents an event?

    • Options
    • A. concrete cured
    • B. fixing of door
    • C. plastering of walls
    • D. selecting sites
    • E. all the above.
    • Discuss
    • 6. Residential buildings are treated as

    • Options
    • A. light construction
    • B. heavy construction
    • C. industrial construction
    • D. private construction.
    • Discuss
    • 7. Railway projects are treated as

    • Options
    • A. light construction
    • B. heavy construction
    • C. industrial construction
    • D. none of these.
    • Discuss
    • 8. An event is indicated on the network by a number enclosed in

    • Options
    • A. a circle
    • B. a square
    • C. a triangle
    • D. an ellipse
    • E. all the above.
    • Discuss
    • 9. The critical activity has

    • Options
    • A. maximum float
    • B. minimum float
    • C. zero float
    • D. none of these.
    • Discuss
    • 10. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

    • Options
    • A. (t1 - t2) - t
    • B. t - (t1 - t2)
    • C. (t1 + t2) - t
    • D. t + (t1 - t2)
    • Discuss


    Comments

    There are no comments.

Enter a new Comment