Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
Options
A. 20
B. 25
C. 35
D. 15
Correct Answer
25
More questions
1. The minimum horizontal distance between two parallel main reinforcing bars, is
Options
A. the diameter of the bar if their diameters are same
B. the diameter of the longer bar if their diameters are unequal
C. 5 mm more than nominal maximum size of the coarse aggragate
Correct Answer: both longitudinal and cross sections are required
7. An R.C.C. column of 30 cm diameter is reinforced with 6 bars 12 mm ? placed symmetrically along the circumference. If it carries a load of 40, 000 kg axially, the stress is