logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Construction Management Comments

  • Question
  • For the network shown in the given figure, the expected time for the activity
    For the network shown in the given figure, the expected time for the activity 1-2 is 4 2-3 is 7 3-4


  • Options
  • A. 1-2 is 4
  • B. 2-3 is 7
  • C. 3-4 is 8
  • D. all the above.

  • Correct Answer
  • all the above. 

    Explanation
    Expected time = (Pessimistic value + 4*most likely value + Optimistic value)/6.

    1-2 is 4.

    2-3 is 7.

    3-4 is 8.


    Construction Management problems


    Search Results


    • 1. Pick up the incorrect statement from the following:

    • Options
    • A. The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
    • B. The difference between the maximum time available for the job and actual time it consumes, is called total float
    • C. The difference between the latest start time and earliest start time of an activity, is called total float
    • D. The difference between the earliest finish time of an activity and the earliest start time of its successor activity, is called free float of the activity
    • E. None of these.
    • Discuss
    • 2. The final selection of a construction site, is done by

    • Options
    • A. departmental representative or user
    • B. local civil authority representative
    • C. representative of engineer authority
    • D. representative of administration
    • E. all the above.
    • Discuss
    • 3. For the execution of a project, a contractor is

    • Options
    • A. a person
    • B. a firm
    • C. an agency
    • D. all the above.
    • Discuss
    • 4. Which one of the following represents an event?

    • Options
    • A. concrete cured
    • B. fixing of door
    • C. plastering of walls
    • D. selecting sites
    • E. all the above.
    • Discuss
    • 5. A goiden rule for the procurement of construction stones, suggests

    • Options
    • A. 100% at the site
    • B. 67% at the site and 33% under procurement
    • C. 50% at the site and 50% under procurement
    • D. 33% at the site and 67% under procurement
    • E. none of these.
    • Discuss
    • 6. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

    • Options
    • A. 20
    • B. 25
    • C. 35
    • D. 15
    • Discuss
    • 7. Residential buildings are treated as

    • Options
    • A. light construction
    • B. heavy construction
    • C. industrial construction
    • D. private construction.
    • Discuss
    • 8. Railway projects are treated as

    • Options
    • A. light construction
    • B. heavy construction
    • C. industrial construction
    • D. none of these.
    • Discuss
    • 9. An event is indicated on the network by a number enclosed in

    • Options
    • A. a circle
    • B. a square
    • C. a triangle
    • D. an ellipse
    • E. all the above.
    • Discuss
    • 10. The critical activity has

    • Options
    • A. maximum float
    • B. minimum float
    • C. zero float
    • D. none of these.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment