  • Pick up the correct statement from the following:


  • Options
  • A. Earliest expected time is denoted by TE
  • B. Latest occurrence time is denoted by TL
  • C. Contractual obligation time is denoted by Ts
  • D. Latest occurrence time is taken as contractual obligation time
  • E. All the above.

  • Correct Answer
  • All the above. 


  • Construction Management problems


    Search Results


    • 1. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

    • Options
    • A. 19
    • B. 14
    • C. 24
    • D. None of these.
    • Discuss
    • 2. Pick up the correct statement from the following:

    • Options
    • A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
    • B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
    • C. The float which affects neither the processor nor the successor activities, is called independent float
    • D. The difference between total float and free float, is called interfering float
    • E. All the above.
    • Discuss
    • 3. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

    • Options
    • A. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
    • B. Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
    • C. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
    • D. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
    • E. All the above.
    • Discuss
    • 4. Pick up the correct statement from the following:

    • Options
    • A. Optimistic time estimate refers to activities
    • B. Pessimistic time estimate refers to activities
    • C. Most likely time estimate refers to activities
    • D. Expected time estimate refers to activities
    • E. All the above.
    • Discuss
    • 5. Pick up the correct statement from the following:

    • Options
    • A. Programme Evaluation and Review Technique, is event oriented
    • B. Programme Evaluation and Review Technique is not event oriented
    • C. Critical Path Method is event oriented
    • D. Critical Path method is event oriented.
    • Discuss
    • 6. PERT is

    • Options
    • A. an analytic in concept
    • B. limited of event oriented diagrams
    • C. used for research and development projects
    • D. based on three time estimates for activities linking up two events
    • E. all the above.
    • Discuss
    • 7. A goiden rule for the procurement of construction stones, suggests

    • Options
    • A. 100% at the site
    • B. 67% at the site and 33% under procurement
    • C. 50% at the site and 50% under procurement
    • D. 33% at the site and 67% under procurement
    • E. none of these.
    • Discuss
    • 8. Which one of the following represents an event?

    • Options
    • A. concrete cured
    • B. fixing of door
    • C. plastering of walls
    • D. selecting sites
    • E. all the above.
    • Discuss
    • 9. For the execution of a project, a contractor is

    • Options
    • A. a person
    • B. a firm
    • C. an agency
    • D. all the above.
    • Discuss
    • 10. The final selection of a construction site, is done by

    • Options
    • A. departmental representative or user
    • B. local civil authority representative
    • C. representative of engineer authority
    • D. representative of administration
    • E. all the above.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment