logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Construction Management Comments

  • Question
  • Pre-tender stage requires


  • Options
  • A. acquisition of land
  • B. selection of site
  • C. formalisation of alignment of work
  • D. formalisation of designs and preparation of estimate
  • E. all the above.

  • Correct Answer
  • all the above. 


  • Construction Management problems


    Search Results


    • 1. For completion of a project, the critical path of the network represents

    • Options
    • A. minimum time
    • B. maximum time
    • C. maximum cost
    • D. minimum cost.
    • Discuss
    • 2. Pick up the incorrect statement from the following:

    • Options
    • A. The various functions under each activity, are shown by one bar on Bar Charts
    • B. Bar chart establishes the interdependency of one event on another
    • C. Only approximate percentage of the completed work is reported
    • D. None of these,
    • Discuss
    • 3. The main disadvantage of line organisation, is

    • Options
    • A. rigid structure
    • B. extraordinary delay in communications
    • C. top level executions over work
    • D. all the above.
    • Discuss
    • 4. Pick up the correct statement from the following:

    • Options
    • A. Forward pass is used for calculating earliest expected time
    • B. Backward pass is used for calculating the latest occurence time
    • C. Maximum value of earliest expected time is used if there are more than one value of any event
    • D. Minimum value of latest occurrence time is used if there are more than one value of any event
    • E. All the above.
    • Discuss
    • 5. The main advantage of line organisation, is :

    • Options
    • A. effective command and control
    • B. defined responsibilities at all levels
    • C. rigid discipline in the organisation
    • D. ability of quick decision at all levels
    • E. all the above.
    • Discuss
    • 6. Frequency distribution curves

    • Options
    • A. having a single lump, are called uninodal curves
    • B. if symmetrical, are called normal curves
    • C. if not symmetrical, are called skew curves
    • D. all the above.
    • Discuss
    • 7. The first stage of a construction, is

    • Options
    • A. preparation of estimate
    • B. survey of the site
    • C. initiation of proposal
    • D. preparation of tender
    • E. allotment of funds.
    • Discuss
    • 8. Pick up the correct statement from the following:

    • Options
    • A. Programme Evaluation and Review Technique, is event oriented
    • B. Programme Evaluation and Review Technique is not event oriented
    • C. Critical Path Method is event oriented
    • D. Critical Path method is event oriented.
    • Discuss
    • 9. Pick up the correct statement from the following:

    • Options
    • A. Optimistic time estimate refers to activities
    • B. Pessimistic time estimate refers to activities
    • C. Most likely time estimate refers to activities
    • D. Expected time estimate refers to activities
    • E. All the above.
    • Discuss
    • 10. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

    • Options
    • A. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
    • B. Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
    • C. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
    • D. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
    • E. All the above.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment