CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Construction Management
Comments
Question
The main disadvantage of line organisation, is
Options
A. rigid structure
B. extraordinary delay in communications
C. top level executions over work
D. all the above.
Correct Answer
all the above.
Construction Management problems
Search Results
1. Pick up the correct statement from the following:
Options
A. Forward pass is used for calculating earliest expected time
B. Backward pass is used for calculating the latest occurence time
C. Maximum value of earliest expected time is used if there are more than one value of any event
D. Minimum value of latest occurrence time is used if there are more than one value of any event
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
2. The main advantage of line organisation, is :
Options
A. effective command and control
B. defined responsibilities at all levels
C. rigid discipline in the organisation
D. ability of quick decision at all levels
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
3. Pick up the correct statement from the following:
Options
A. The difference of latest occurence time and earliest expected time, is called slack
B. The activities connecting the events having zero slack, lie on the critical path
C. The critical path consumes the maximum time
D. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
4. While filling the tender for any work, the contractor considers
Options
A. site survey
B. availability of construction materials
C. availability of labour
D. study of specifications
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
5. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
Options
A. 1
B. 2
C. 3
D. 4
Show Answer
Scratch Pad
Discuss
Correct Answer: 1
6. Pick up the incorrect statement from the following:
Options
A. The various functions under each activity, are shown by one bar on Bar Charts
B. Bar chart establishes the interdependency of one event on another
C. Only approximate percentage of the completed work is reported
D. None of these,
Show Answer
Scratch Pad
Discuss
Correct Answer: Bar chart establishes the interdependency of one event on another
7. For completion of a project, the critical path of the network represents
Options
A. minimum time
B. maximum time
C. maximum cost
D. minimum cost.
Show Answer
Scratch Pad
Discuss
Correct Answer: minimum time
8. Pre-tender stage requires
Options
A. acquisition of land
B. selection of site
C. formalisation of alignment of work
D. formalisation of designs and preparation of estimate
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
9. Frequency distribution curves
Options
A. having a single lump, are called uninodal curves
B. if symmetrical, are called normal curves
C. if not symmetrical, are called skew curves
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
10. The first stage of a construction, is
Options
A. preparation of estimate
B. survey of the site
C. initiation of proposal
D. preparation of tender
E. allotment of funds.
Show Answer
Scratch Pad
Discuss
Correct Answer: initiation of proposal
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering