logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Railways Comments

  • Question
  • If n is length of a rail in metres, the number of sleepers per rail length generally varies from


  • Options
  • A. n to (n + 2)
  • B. (n + 2) to (n + 4)
  • C. (n + 3) to (n + 6)
  • D. (n + 4) to (n + 5)

  • Correct Answer
  • (n + 3) to (n + 6) 


  • Railways problems


    Search Results


    • 1. Burnettising is done for the preservation of

    • Options
    • A. wooden sleepers
    • B. rails
    • C. ballast
    • D. none of these.
    • Discuss
    • 2. Each block of a two-block concrete sleeper is

    • Options
    • A. 722 mm x 295 mm x 271 mm and 215 kg in weight
    • B. 250 mm x 154 mm x 196 mm and 260 kg in weight
    • C. 525 mm x 350 mm x 275 mm and 280 kg in weight
    • D. none of these.
    • Discuss
    • 3. Wing rails are provided

    • Options
    • A. near tongue rails
    • B. near check rails
    • C. near stock rails
    • D. in crossing.
    • Discuss
    • 4. The rails get out of their original positions due to insufficient expansion gap. This phenomenon is known

    • Options
    • A. hogging
    • B. buckling
    • C. creeping
    • D. none of these.
    • Discuss
    • 5. For points and crossings, maximum size of ballast, is

    • Options
    • A. 50 mm
    • B. 40 mm
    • C. 30 mm
    • D. 25 mm
    • E. 20 mm
    • Discuss
    • 6. If S is the switch angle and ? is diamond angle, r is the radius of slip, the distance between middle point slip and the nose of obtuse crossing, is

    • Options
    • A.
    • B.
    • C.
    • D.
    • Discuss
    • 7. In CPM analysis,

    • Options
    • A. emphasis is given to activities
    • B. uncertainties are not allowed
    • C. activities are represented by arrows
    • D. beginning and end of an activity, are denoted by nodes
    • E. all the above.
    • Discuss
    • 8. PERT analysis is based on

    • Options
    • A. optimistic time
    • B. pessimistic time
    • C. most likely time
    • D. all the above.
    • Discuss
    • 9. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

    • Options
    • A. 1
    • B. 2
    • C. 3
    • D. 4
    • Discuss
    • 10. While filling the tender for any work, the contractor considers

    • Options
    • A. site survey
    • B. availability of construction materials
    • C. availability of labour
    • D. study of specifications
    • E. all the above.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment