For efficient working of a sewer, it must be ensured that
Options
A. minimum velocity of 0.45 m/sec, is maintained at its minimum flow
B. a maximum velocity of 0.90 m/sec, is maintained at its maximum flow
C. both (a) and (b)
D. neither (a) nor (b).
Correct Answer
both (a) and (b)
More questions
1. If the normal stresses due to longitudinal and transverse loads on a bar are ?1 and ?2 respectively, the tangential component of the stress on an inclined plane through ?°, the longitudinal load is
3. It is proposed to widen and strengthen an existing 2-lane NH section as a divided highway. The existing traffic in one direction is 2500 commercial vehicles (CV) per day. The construction will take 1 year. The design CBR of soil subgrade is found to be 5 percent, Given: traffic growth rate for CV = 8 percent, vehicle damage factor = 3.5 (standard axles per CV), design life = 10 years and traffic distribution factor = 0.75. The cumulative standard axles (msa) computed are
4. In a simply supported beam (l + 2a) with equal overhangs (a) and carrying a uniformly distributed load over its entire length, B.M. at the middle point of the beam will be zero if
9. Long and short spans of a two way slab are ly and lx and load on the slab acting on strips parallel to lx and ly be wx and wy respectively. According to Rankine Grashoff theory