  • For setting out a simple curve, using two theodolites.


  • Options
  • A. offsets from tangents are required
  • B. offsets from chord produced are required
  • C. offsets from long chord are required
  • D. deflection angles from Rankine's formula are required
  • E. none of these.

  • Correct Answer
  • none of these. 


  • Surveying problems


    Search Results


    • 1. True meridian of different places

    • Options
    • A. converge from the south pole to the north pole
    • B. converge from the north pole to the south pole
    • C. converge from the equator to the poles
    • D. run parallel to each other.
    • Discuss
    • 2. If the rate of gain of radial acceleration is 0.3 m per sec3 and full centrifugal ratio is developed. On the curve the ratio of the length of the transition curve of same radius on road and railway, is

    • Options
    • A. 2.828
    • B. 3.828
    • C. 1.828
    • D. 0.828.
    • Discuss
    • 3. Probable systematic error in precise levelling as recommended by International Geodetic Association should not exceed
      (where k is in kilometers.)

    • Options
    • A. ± 0.1 k mm
    • B. ± 0.2 k mm
    • C. ± 0.1 k
    • D. 0.2 k mm.
    • Discuss
    • 4. The latitude of a traverse leg is obtained by multiplying its length by

    • Options
    • A. tangent of its reduced bearing
    • B. sign of its reduced bearing
    • C. cosine of its reduced bearing
    • D. cosecant of its reduced bearing.
    • Discuss
    • 5. The branch of surveying in which both horizontal and vertical positions of a point, are determined by making instrumental observations, is known

    • Options
    • A. tacheometry
    • B. tachemetry
    • C. telemetry
    • D. all the above.
    • Discuss
    • 6. Orientation of a plane table by solving two point problem is only adopted when

    • Options
    • A. saving of time is a main factor
    • B. better accuracy is a main factor
    • C. given points are inaccessible
    • D. none of these.
    • Discuss
    • 7. Measuring with a 30 m chain, 0.01 m too short, introduces

    • Options
    • A. positive compensating error
    • B. negative compensating error
    • C. positive cumulative error
    • D. negative cumulative error.
    • Discuss
    • 8. A uniform slope was measured by the method of stepping. If the difference in level between two points is 1.8 m and the slope distance between them is 15 m, the error is approximately equal to

    • Options
    • A. cumulative, + 0.11 m
    • B. compensating, ± 0.11 m
    • C. cumulative, - 0.11 m
    • D. none of these
    • Discuss
    • 9. Keeping the instrument height as 1 m, length of staff 4 m, the up gradient of the ground 1 in 10, the sight on the up slope must be less than

    • Options
    • A. 25 cm
    • B. 20 m
    • C. 45 m
    • D. 10 m
    • Discuss
    • 10. For a curve of radius 100 m and normal chord 10 m, the Rankine's deflection angle, is

    • Options
    • A. 0°25'.95
    • B. 0°35'.95
    • C. 1°25'.53
    • D. 1°35'.95
    • E. 2°51'.53.
    • Discuss