  • Critical path of the PERT chart is:


  • Options
  • A. path which takes the longest time to complete the project
  • B. the shortest path
  • C. both of the above
  • D. path which takes the shortest time to complete the project
  • E. None of the above

  • Correct Answer
  • path which takes the longest time to complete the project 


  • Management Information Systems problems


    Search Results


    • 1. Error reports are an example of:

    • Options
    • A. scheduled reports
    • B. demand reports
    • C. exception reports
    • D. predictive reports
    • E. management reports
    • Discuss
    • 2. The online, softcopy display of a customer's charge account to respond to an inquiry is an example of a(n):

    • Options
    • A. regularly scheduled report
    • B. on-demand report
    • C. exception report
    • D. forecasting report
    • E. None of the above
    • Discuss
    • 3. A _____ is a brief message to an operator that describes what data are to be entered.

    • Options
    • A. prompt
    • B. passwords
    • C. MIS
    • D. Tactical
    • E. None of the above
    • Discuss
    • 4. Order-filling activity in the physical system is triggered by the

    • Options
    • A. manufacturing information system
    • B. order entry subsystem
    • C. billing subsystem
    • D. accounts receivable subsystem
    • E. None of the above
    • Discuss
    • 5. Controls of data communication deal with

    • Options
    • A. the communication channel
    • B. the computer
    • C. terminals
    • D. All of the above
    • E. None of the above
    • Discuss
    • 6. The four major corporate resources are money, materials, information, and

    • Options
    • A. people
    • B. icons
    • C. information system
    • D. on-line
    • E. None of the above
    • Discuss
    • 7. _____ are knowledge based system to which present rules are applied to solve a particular problem.

    • Options
    • A. ES
    • B. AI
    • C. KBS
    • D. Base rule 0
    • E. None of the above
    • Discuss
    • 8. An optional facilitates location program can be used to study

    • Options
    • A. factory location alternative
    • B. warehouse location alternatives
    • C. plant location alternatives
    • D. All of the above
    • E. None of the above
    • Discuss
    • 9. The product structure file is also called the

    • Options
    • A. item master file
    • B. bill of materials file
    • C. operations file
    • D. All of the above
    • E. None of the above
    • Discuss
    • 10. Which of the following is not an important principle for evaluating the raw data for decision-making:

    • Options
    • A. selection
    • B. pattern
    • C. everage
    • D. overview
    • E. None of the above
    • Discuss


    Comments

    There are no comments.

Enter a new Comment