CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Tunnelling
Comments
Question
The advantages of providing a pair of tunnels as compared to only one large highway tunnel is :
Options
A. economy in cost of construction
B. avoidance of head on collisions
C. provision of separate exit and entrance of two traffic streams
D. facility in carrying out repairs
E. All the above.
Correct Answer
All the above.
Tunnelling problems
Search Results
1. In the given figure drill holes, heading, mucking and benching are mumbered as 1, 2, 3, 4 The correct sequence is :
Options
A. 4 1 2 3
B. 1 2 3 4
C. 4 1 3 2
D. 3 4 1 3
Show Answer
Scratch Pad
Discuss
Correct Answer: 4 1 3 2
2. Railway tunnels, are generally
Options
A. polycentric
B. rectangular
C. parabolic
D. circular
E. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: polycentric
3. For tunnels exceeding 300 m in length, the grade should be provided below
Options
A. 50% of the ruling gradient
B. 60% of the ruling gradient
C. 75% of the ruling gradient
D. 80% of the ruling gradient.
Show Answer
Scratch Pad
Discuss
Correct Answer: 75% of the ruling gradient
4. Pick up the correct statement regarding drilling a tunnel from the following:
Options
A. Holes are drilled by pneumatically operated rock drills
B. One drill is required for each 4 to 5 m
2
force area
C. The diameter of the bore hole at the deepest point should be 6 mm more than the diameter of the cartridge
D. All of the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All of the above.
5. The method of draining in the tunnels, is generally known as
Options
A. foredrainage
B. dewatering
C. permanent drainage
D. All of the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All of the above.
6. For full face method, the excavation to be done is generally divided into
Options
A. two sections
B. three sections
C. four sections
D. five sections.
Show Answer
Scratch Pad
Discuss
Correct Answer: three sections
7. The concentration of the dust particles of the size 0.5 to 5 microns adjacent to the working face should not be more than
Options
A. 200 particles/cm
3
B. 250 particles/cm
3
C. 300 particles/cm
3
D. 450 particles/cm
3
E. 400 particles/cm
3
Show Answer
Scratch Pad
Discuss
Correct Answer: 450 particles/cm
3
8. A tunnel is found more advantageous as compared to the alternate routes because it:
Options
A. remains free from snow
B. reduces the cost by reducing the route distance
C. reduces the maintenance cost
D. avoids interference with surface rights
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
9. In case of railways,
Options
A. a detour round the hill is preferred
B. a open cut is preferred
C. tunnelling is preferred
D. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: tunnelling is preferred
10. The following operations are required for tunnelling in rocky terrain :
1. Removing the foul gases
2. Marking the tunnel profile
3. Setting up and drilling
4. Checking misfire
5. Mucking
The correct sequence is :
Options
A. 1 2 3 4 5
B. 2 3 5 4 1
C. 4 2 1 3 5
D. 2 3 1 4 5
Show Answer
Scratch Pad
Discuss
Correct Answer: 2 3 1 4 5
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering