  • Question
  • In the given figure drill holes, heading, mucking and benching are mumbered as 1, 2, 3, 4 The correct sequence is :
    In the given figure drill holes, heading, mucking and benching are mumbered as 1, 2, 3, 4 The correc


  • Options
  • A. 4 1 2 3
  • B. 1 2 3 4
  • C. 4 1 3 2
  • D. 3 4 1 3

  • Correct Answer
  • 4 1 3 2 


  • Tunnelling problems


    Search Results


    • 1. Railway tunnels, are generally

    • Options
    • A. polycentric
    • B. rectangular
    • C. parabolic
    • D. circular
    • E. none of these.
    • Discuss
    • 2. For tunnels exceeding 300 m in length, the grade should be provided below

    • Options
    • A. 50% of the ruling gradient
    • B. 60% of the ruling gradient
    • C. 75% of the ruling gradient
    • D. 80% of the ruling gradient.
    • Discuss
    • 3. Pick up the correct statement regarding drilling a tunnel from the following:

    • Options
    • A. Holes are drilled by pneumatically operated rock drills
    • B. One drill is required for each 4 to 5 m2 force area
    • C. The diameter of the bore hole at the deepest point should be 6 mm more than the diameter of the cartridge
    • D. All of the above.
    • Discuss
    • 4. The method of draining in the tunnels, is generally known as

    • Options
    • A. foredrainage
    • B. dewatering
    • C. permanent drainage
    • D. All of the above.
    • Discuss
    • 5. The following operations are generally employed for tunnelling in hard rock.
      1. Removing ground water,
      2. Loading holes and firing the explosive
      3. Setting up and drilling
      4. Grouting and lining
      5. Removing muck
      6. Ventilation and removing explosion dust
      The correct sequence is :

    • Options
    • A. 3 2 6 5 1 4
    • B. 3 4 6 1 5 2
    • C. 4 1 2 3 6 5
    • D. 5 4 2 1 3 6
    • Discuss
    • 6. The advantages of providing a pair of tunnels as compared to only one large highway tunnel is :

    • Options
    • A. economy in cost of construction
    • B. avoidance of head on collisions
    • C. provision of separate exit and entrance of two traffic streams
    • D. facility in carrying out repairs
    • E. All the above.
    • Discuss
    • 7. For full face method, the excavation to be done is generally divided into

    • Options
    • A. two sections
    • B. three sections
    • C. four sections
    • D. five sections.
    • Discuss
    • 8. The concentration of the dust particles of the size 0.5 to 5 microns adjacent to the working face should not be more than

    • Options
    • A. 200 particles/cm3
    • B. 250 particles/cm3
    • C. 300 particles/cm3
    • D. 450 particles/cm3
    • E. 400 particles/cm3
    • Discuss
    • 9. A tunnel is found more advantageous as compared to the alternate routes because it:

    • Options
    • A. remains free from snow
    • B. reduces the cost by reducing the route distance
    • C. reduces the maintenance cost
    • D. avoids interference with surface rights
    • E. All the above.
    • Discuss
    • 10. In case of railways,

    • Options
    • A. a detour round the hill is preferred
    • B. a open cut is preferred
    • C. tunnelling is preferred
    • D. All the above.
    • Discuss