logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Concrete Technology Comments

  • Question
  • M10 grade of concrete approximates


  • Options
  • A. 1 : 3 : 6 mix
  • B. 1 : 1 : 2 mix
  • C. 1 : 2 : 4 mix
  • D. 1 : 1.5 : 3 mix
  • E. none of these.

  • Correct Answer
  • 1 : 3 : 6 mix 


  • Concrete Technology problems


    Search Results


    • 1. To obtain cement dry powder, lime stones and shales or their slurry, is burnt in a rotary kiln at a temperature between

    • Options
    • A. 1100° and 1200°C
    • B. 1200° and 1300°C
    • C. 1300° and 1400°C
    • D. 1400° and 1500°C
    • E. 1500° and 1600°C
    • Discuss
    • 2. The increased cohesiveness of concrete, makes it

    • Options
    • A. less liable to segregation
    • B. more liable to segregation
    • C. more liable to bleeding
    • D. more liable for surface scaling in frosty weather
    • E. none of these.
    • Discuss
    • 3. If 1500 g of water is required to have a cement paste 1875 g of normal consistency, the percentage of water is,

    • Options
    • A. 20%
    • B. 25%
    • C. 30%
    • D. 35%
    • E. 40%
    • Discuss
    • 4. The following proportion of the ingredients of concrete mix, is not in conformation to arbitrary method of proportioning

    • Options
    • A. 1 : 1 : 2
    • B. 1 : 2 : 4
    • C. 1 : 3 : 6
    • D. 1 : 2 : 8
    • E. 1 : 4 : 10
    • Discuss
    • 5. Curing a concrete for long period ensures better

    • Options
    • A. volume stability
    • B. strength
    • C. water resistance
    • D. water tightness and durability
    • E. all the above.
    • Discuss
    • 6. The rock which is not calcareous, is :

    • Options
    • A. lime stone
    • B. macl
    • C. chalk
    • D. laterite
    • E. none of these.
    • Discuss
    • 7. Under normal conditions using an ordinary cement, the period of removal of the form work, is :

    • Options
    • A. 7 days for beam soffits
    • B. 14 days for bottom slabs of spans 4.6 m and more
    • C. 21 days for bottom beams over 6 m spans
    • D. 2 days for vertical sides of columns
    • E. all the above.
    • Discuss
    • 8. The standard sand now a days used in India, is obtained from

    • Options
    • A. Jaipur (Rajasthan)
    • B. Jullundur (Punjab)
    • C. Hyderabad (Andhra Pradesh)
    • D. Ennore (Madras)
    • E. Cuttuck (Orissa).
    • Discuss
    • 9. Transport of concrete by pumps, is done for a distance of

    • Options
    • A. 100 m
    • B. 200 m
    • C. 300 m
    • D. 400 m
    • E. none of these.
    • Discuss
    • 10. An aggregate is said to be flaky if its least dimension is less than

    • Options
    • A. 1/5th of mean dimension
    • B. 2/5th of mean dimension
    • C. 3/5th of mean dimension
    • D. 4/5th of mean dimension
    • E. none of these.
    • Discuss