logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Estimating and Costing Comments

  • Question
  • Pick up the correct statement from the following:


  • Options
  • A. The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
  • B. The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
  • C. The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
  • D. All the above.

  • Correct Answer
  • All the above. 


  • Estimating and Costing problems


    Search Results


    • 1. Pick up the incorrect statement from the following:

    • Options
    • A. Dimensions are measured to the nearest 0.01 m
    • B. Areas are measured to the nearest 0.01 sq.m
    • C. Cubic contents are measured to the nearest 0.1 cm m
    • D. Weights are measured to the nearest 0.001 tonnes
    • Discuss
    • 2. The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is

    • Options
    • A. (6 + 15) chains
    • B. (6 + 12) chains
    • C. (6 + 18) chains
    • D. None of these.
    • Discuss
    • 3. The value of 'C' of Indian type W.C. shown in the given figure is :

    • Options
    • A. 400 mm
    • B. 450 mm
    • C. 500 mm
    • D. 550 mm
    • Discuss
    • 4. The damp proof course (D.P.C.) is measured in

    • Options
    • A. Cub.m
    • B. Sq m
    • C. Metres
    • D. None of these
    • Discuss
    • 5. While estimating a reinforced cement structure, the omitted cover of concrete is assumed

    • Options
    • A. at the end of reminforcing bar, not less than 25 mm or twice the diameter of the bar
    • B. in thin slabs, 12 mm minimum or diameter of the bar whichever is more
    • C. for reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more
    • D. All the above.
    • Discuss
    • 6. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and

    • Options
    • A. breadth of the wall
    • B. half breadth of wall on each side
    • C. one fourth breadth of wall on each side
    • D. None of these.
    • Discuss
    • 7. According to ISI method of measurement, the order of the sequence is

    • Options
    • A. Length, breadth, height
    • B. Breadth, length, height
    • C. Height, length, breadth
    • D. None of these.
    • Discuss
    • 8. The inspection pit or chamber is a manhole provided in a base drainage system

    • Options
    • A. at every change of direction
    • B. at every change of gradient
    • C. at every 30 m intervals
    • D. at the point where vertical soil pipe joins the house drain
    • E. All the above.
    • Discuss
    • 9. The most reliable estiamte is

    • Options
    • A. Detailed estimate
    • B. Preliminary estimate
    • C. Plinth area estimate
    • D. Cube rate estimate
    • E. None of these.
    • Discuss
    • 10. The measurement is not made in square metres in case of

    • Options
    • A. D.P.C. (Damp proof course)
    • B. Form works
    • C. Concrete Jaffries
    • D. R.C. Chhajja.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment