logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Estimating and Costing Comments

  • Question
  • The order of booking dimensions is


  • Options
  • A. Length, breadth, height
  • B. Breadth, length, height
  • C. Height, breadth, length
  • D. None of these.

  • Correct Answer
  • Length, breadth, height 


  • Estimating and Costing problems


    Search Results


    • 1. Pick up the excavation where measurements are made in square metres for payment.

    • Options
    • A. Ordinary cuttings up to 1 m
    • B. surface dressing up to 15 cm depths
    • C. Surface excavation up to 30 cm depths
    • D. Both (b) and (c)
    • E. Both (a) and (b)
    • Discuss
    • 2. The item of steel work which is measured in sq.m, is

    • Options
    • A. Collapsible gates
    • B. Rolling shutters
    • C. Steel doors
    • D. Ventilators and glazing.
    • E. All the above.
    • Discuss
    • 3. In the mid-section formula

    • Options
    • A. The mean depth is the average of depths of two consecutive sections
    • B. The area of mid-sections is calculated by using mean depth
    • C. The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two sections
    • D. The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
    • E. (a), (b) and (c) of the above.
    • Discuss
    • 4. Pick up the incorrect statement regarding a master trap from the following :

    • Options
    • A. It is provided in between the lower end of the house drain and the street sewer
    • B. It is provided a cleaning eye at the top of the trap
    • C. The height of fresh air inlet pipe fixed vertically with wall is 3 m
    • D. The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe
    • E. The water seal is less than that of ordinary traps.
    • Discuss
    • 5. The assumption on which the trapezoidal formula for volumes is based, is

    • Options
    • A. The end sections are parallel planes
    • B. The mid-area of a pyramid is half the average area of the ends
    • C. The volume of the prismoidal is over-es-timted and hence a prismoidal correction is applied
    • D. All the above.
    • Discuss
    • 6. The item of the brick structure measured in sq.m, is

    • Options
    • A. Reinforced brick work
    • B. Broken glass coping
    • C. Brick edging
    • D. Brick work in arches.
    • Discuss
    • 7. The expected out turn of 2.5 cm cement concrete floor per manson per day

    • Options
    • A. 2.5 sqm
    • B. 5.0 sqm
    • C. 7.5 sqm
    • D. 10 sqm
    • Discuss
    • 8. The detention period in a septic tank is assumed

    • Options
    • A. 20 minutes
    • B. 25 minutes
    • C. 30 minutes
    • D. 40 minutes
    • Discuss
    • 9. Pick up the correct statement in case of water supply.

    • Options
    • A. Pipes laid in trenches and pipes fixed to walls are measured separately
    • B. Cutting through walls and floors are included with the item
    • C. Pipes are classified according to their sizes and quality
    • D. In laying pipes, the method of jointing and fixing is specifically specified
    • E. All the above.
    • Discuss
    • 10. The volume is measured correct to the nearest

    • Options
    • A. 0.01 cum
    • B. 0.02 cum
    • C. 0.03 cum
    • D. 0.04 cum
    • E. 0.05 sum
    • Discuss


    Comments

    There are no comments.

Enter a new Comment