Home Civil Engineering Construction Management Comments

  • Question
  • A CPM family includes


  • Options
  • A. CPA (Critical Path Analysis)
  • B. CPP (Critical Path Plotted)
  • C. MCE (Minimum Cost Expenditure)
  • D. CPS (Critical Path Scheduling)
  • E. All the above.

  • Correct Answer
  • All the above. 


  • Construction Management problems


    Search Results


    • 1. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:

    • Options
    • A. 1. Pouring of Concrete
      2. Erection of form work
      3. Curing of concrete
      4. Removal of form work
    • B. 1. Erection of form work
      2. Pouring of concrete
      3. Curing of concrete
      4. Removal of form work
    • C. 1. Removal of form work
      2. Erection of form work
      3. Pouring of concrete
      4. Curing of concrete
    • D. 1. Pouring of concrete
      2. Curing of concrete
      3. Erection of form work
      4. Removal of form work
    • Discuss
    • 2. Critical Path Net Work helps an engineer

    • Options
    • A. to concentrate his attention on critical activities
    • B. to divert the resources from non-critical advanced activities to critical activities
    • C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
    • D. all the above.
    • Discuss
    • 3. Military organisation is known as

    • Options
    • A. line organisation
    • B. line and staff organisation
    • C. functional organisation
    • D. none of these.
    • Discuss
    • 4. Final technical authority of a project lies with

    • Options
    • A. Assistant Engineer
    • B. Executive Engineer
    • C. Superintending Engineer
    • D. Chief Engineer.
    • Discuss
    • 5. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

    • Options
    • A. duration
    • B. total flat
    • C. free float
    • D. interfering float.
    • Discuss
    • 6. Pick up the correct statement from the following:

    • Options
    • A. The float may be positive, zero or negative
    • B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
    • C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
    • D. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
    • E. All the above.
    • Discuss
    • 7. The performance of a specific task in CPM, is known

    • Options
    • A. Dummy
    • B. Event
    • C. Activity
    • D. Contract.
    • Discuss
    • 8. A dummy activity

    • Options
    • A. is artificially introduced
    • B. is represented by a dotted line
    • C. does not consume time
    • D. all the above.
    • Discuss
    • 9. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

    • Options
    • A. EF = ES + D
    • B. LS = LF - D
    • C. LF = LS + D
    • D. D = EF - ES
    • E. all the above.
    • Discuss
    • 10. Critical path method

    • Options
    • A. is an improvement upon bar chart method
    • B. provides a realistic approach to daily problems
    • C. avoids delays which are very common in bar charts
    • D. was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957
    • E. All the above.
    • Discuss