logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Construction Management Comments

  • Question
  • If TL is the latest allowable event occurrence time, total activity slack(s), is equal to


  • Options
  • A. LST-EST
  • B. LFT-EFT
  • C. TL-EFT
  • D. all the above.

  • Correct Answer
  • all the above. 


  • Construction Management problems


    Search Results


    • 1. Pick up the correct statement from the following:

    • Options
    • A. CPM analysis is activity oriented
    • B. PERT analysis is event oriented
    • C. CPM does not make any allowance for the uncertainties in the duration of time
    • D. In CPM, the time is related to cost
    • E. All the above.
    • Discuss
    • 2. The technique for establishing and maintaining priorities among the various jobs of a project, is known

    • Options
    • A. Event flow scheduling technique
    • B. Critical ratio scheduling
    • C. Slotting technique for scheduling
    • D. Short interval scheduling.
    • Discuss
    • 3. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

    • Options
    • A.
    • B.
    • C.
    • D.
    • Discuss
    • 4. Frederick W. Taylor introduced a system of working known as

    • Options
    • A. line organisation
    • B. line and staff organisation
    • C. functional organisation
    • D. effective organisation.
    • Discuss
    • 5. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

    • Options
    • A. started 5 days later
    • B. completed 5 days later
    • C. performed at slower rate in 15 days
    • D. all the above.
    • Discuss
    • 6. Works costing less than Rs. 20,000 are treated as

    • Options
    • A. projects
    • B. major projects
    • C. minor projects
    • D. all the above.
    • Discuss
    • 7. Various activities of a project, are shown on bar charts by

    • Options
    • A. vertical lines
    • B. horizontal lines
    • C. dots
    • D. crosses.
    • Discuss
    • 8. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

    • Options
    • A. duration
    • B. total flat
    • C. free float
    • D. interfering float.
    • Discuss
    • 9. Final technical authority of a project lies with

    • Options
    • A. Assistant Engineer
    • B. Executive Engineer
    • C. Superintending Engineer
    • D. Chief Engineer.
    • Discuss
    • 10. Military organisation is known as

    • Options
    • A. line organisation
    • B. line and staff organisation
    • C. functional organisation
    • D. none of these.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment