CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Construction Management
Comments
Question
Pick up the correct statement from the following:
Options
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. CPM does not make any allowance for the uncertainties in the duration of time
D. In CPM, the time is related to cost
E. All the above.
Correct Answer
All the above.
Construction Management problems
Search Results
1. The technique for establishing and maintaining priorities among the various jobs of a project, is known
Options
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling.
Show Answer
Scratch Pad
Discuss
Correct Answer: Critical ratio scheduling
2. If
a
is the optimistic time,
b
is the pessimistic time and
m
is most likely time of an activity, the expected time of the activity, is
Options
A.
B.
C.
D.
Show Answer
Scratch Pad
Discuss
Correct Answer:
3. Frederick W. Taylor introduced a system of working known as
Options
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation.
Show Answer
Scratch Pad
Discuss
Correct Answer: functional organisation
4. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
Options
A. started 5 days later
B. completed 5 days later
C. performed at slower rate in 15 days
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
5. Pick up the incorrect statement from the following:
Options
A. The activity is the time consuming part of a project
B. The beginning and end of a job, are called events
C. The activity which consumes maximum time, is called a node
D. Logically and sequentially connected activities and events form a network
E. None of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: The activity which consumes maximum time, is called a node
6. If
TL
is the latest allowable event occurrence time, total activity slack(s), is equal to
Options
A.
LST-EST
B.
LFT-EFT
C.
TL-EFT
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
7. Works costing less than Rs. 20,000 are treated as
Options
A. projects
B. major projects
C. minor projects
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: minor projects
8. Various activities of a project, are shown on bar charts by
Options
A. vertical lines
B. horizontal lines
C. dots
D. crosses.
Show Answer
Scratch Pad
Discuss
Correct Answer: horizontal lines
9. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
Options
A. duration
B. total flat
C. free float
D. interfering float.
Show Answer
Scratch Pad
Discuss
Correct Answer: free float
10. Final technical authority of a project lies with
Options
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer.
Show Answer
Scratch Pad
Discuss
Correct Answer: Chief Engineer.
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering