CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Construction Management
Comments
Question
The estimated time required to perform an activity, is known as
Options
A. event
B. dummy
C. duration
D. float.
Correct Answer
duration
Construction Management problems
Search Results
1. Mile Stone charts were invented in the year of
Options
A. 1910
B. 1920
C. 1930
D. 1940
E. 1950
Show Answer
Scratch Pad
Discuss
Correct Answer: 1940
2. In the given figure, the network of a project represents
Options
A. activity of an excavation of a footing
B. activity of an excavation which starts at event No. 1 and ends at even No. 2
C. activity of excavation which takes 8 units of time
D. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: activity of excavation which takes 8 units of time
3. Bar charts are suitable for
Options
A. minor works
B. major works
C. large projects
D. all the Above.
Show Answer
Scratch Pad
Discuss
Correct Answer: minor works
4. The most popular type of organisation used for Civil Engineering Constructions, is
Options
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation.
Show Answer
Scratch Pad
Discuss
Correct Answer: line organisation
5. Which one of the following represents an activity
Options
A. excavation for foundation
B. curing of concrete
C. setting of question paper
D. preparation of breakfast
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
6. Time and progress chart of a construction, is also known as
Options
A. Bar chart
B. Gantt chart
C. Modified Mile stone chart
D. Critical path method chart
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
7. The first method invented for planning projects, was
Options
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)
Show Answer
Scratch Pad
Discuss
Correct Answer: Bar chart method
8. The difference between the time avail-to do a job and the time required to do the job, is known as
Options
A. event
B. float
C. duration
D. constraint.
Show Answer
Scratch Pad
Discuss
Correct Answer: float
9. If
t
o
,
t
p
and
t
m
are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time
t
of the activity will be
Options
A.
B.
C.
D.
E.
Show Answer
Scratch Pad
Discuss
Correct Answer:
10. A critical ratio scheduling
Options
A. establishes the relative priorities among various activities on a common basis
B. determines the status of each activity
C. adjusts automatically changes in activity progress
D. is a dynamic system
E. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: none of these.
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering