logo

CuriousTab

CuriousTab

Discussion


Home Civil Engineering Construction Management Comments

  • Question
  • The estimated time required to perform an activity, is known as


  • Options
  • A. event
  • B. dummy
  • C. duration
  • D. float.

  • Correct Answer
  • duration 


  • Construction Management problems


    Search Results


    • 1. Mile Stone charts were invented in the year of

    • Options
    • A. 1910
    • B. 1920
    • C. 1930
    • D. 1940
    • E. 1950
    • Discuss
    • 2. In the given figure, the network of a project represents

    • Options
    • A. activity of an excavation of a footing
    • B. activity of an excavation which starts at event No. 1 and ends at even No. 2
    • C. activity of excavation which takes 8 units of time
    • D. none of these.
    • Discuss
    • 3. Bar charts are suitable for

    • Options
    • A. minor works
    • B. major works
    • C. large projects
    • D. all the Above.
    • Discuss
    • 4. The most popular type of organisation used for Civil Engineering Constructions, is

    • Options
    • A. line organisation
    • B. line and staff organisation
    • C. functional organisation
    • D. effective organisation.
    • Discuss
    • 5. Which one of the following represents an activity

    • Options
    • A. excavation for foundation
    • B. curing of concrete
    • C. setting of question paper
    • D. preparation of breakfast
    • E. all the above.
    • Discuss
    • 6. Time and progress chart of a construction, is also known as

    • Options
    • A. Bar chart
    • B. Gantt chart
    • C. Modified Mile stone chart
    • D. Critical path method chart
    • E. All the above.
    • Discuss
    • 7. The first method invented for planning projects, was

    • Options
    • A. Bar chart method
    • B. Milestone chart
    • C. Critical path method (CPM)
    • D. Programme Evaluation and Review Technique (PERT)
    • Discuss
    • 8. The difference between the time avail-to do a job and the time required to do the job, is known as

    • Options
    • A. event
    • B. float
    • C. duration
    • D. constraint.
    • Discuss
    • 9. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

    • Options
    • A.
    • B.
    • C.
    • D.
    • E.
    • Discuss
    • 10. A critical ratio scheduling

    • Options
    • A. establishes the relative priorities among various activities on a common basis
    • B. determines the status of each activity
    • C. adjusts automatically changes in activity progress
    • D. is a dynamic system
    • E. none of these.
    • Discuss


    Comments

    There are no comments.

Enter a new Comment