  • Question
  • In the given figure, the network of a project represents
    In the given figure, the network of a project represents activity of an excavation of a footing acti


  • Options
  • A. activity of an excavation of a footing
  • B. activity of an excavation which starts at event No. 1 and ends at even No. 2
  • C. activity of excavation which takes 8 units of time
  • D. none of these.

  • Correct Answer
  • activity of excavation which takes 8 units of time 


  • Construction Management problems


    Search Results


    • 1. Bar charts are suitable for

    • Options
    • A. minor works
    • B. major works
    • C. large projects
    • D. all the Above.
    • Discuss
    • 2. The most popular type of organisation used for Civil Engineering Constructions, is

    • Options
    • A. line organisation
    • B. line and staff organisation
    • C. functional organisation
    • D. effective organisation.
    • Discuss
    • 3. Which one of the following represents an activity

    • Options
    • A. excavation for foundation
    • B. curing of concrete
    • C. setting of question paper
    • D. preparation of breakfast
    • E. all the above.
    • Discuss
    • 4. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

    • Options
    • A. event
    • B. free float
    • C. dummy
    • D. constant
    • Discuss
    • 5. The salient feature of functional organisation is

    • Options
    • A. strict adherence to specifications
    • B. separation of planning and design part
    • C. each individual maintains functional efficiency
    • D. work is properly planned and distributed
    • E. all the above.
    • Discuss
    • 6. Mile Stone charts were invented in the year of

    • Options
    • A. 1910
    • B. 1920
    • C. 1930
    • D. 1940
    • E. 1950
    • Discuss
    • 7. The estimated time required to perform an activity, is known as

    • Options
    • A. event
    • B. dummy
    • C. duration
    • D. float.
    • Discuss
    • 8. Time and progress chart of a construction, is also known as

    • Options
    • A. Bar chart
    • B. Gantt chart
    • C. Modified Mile stone chart
    • D. Critical path method chart
    • E. All the above.
    • Discuss
    • 9. The first method invented for planning projects, was

    • Options
    • A. Bar chart method
    • B. Milestone chart
    • C. Critical path method (CPM)
    • D. Programme Evaluation and Review Technique (PERT)
    • Discuss
    • 10. The difference between the time avail-to do a job and the time required to do the job, is known as

    • Options
    • A. event
    • B. float
    • C. duration
    • D. constraint.
    • Discuss