Home Civil Engineering Construction Management Comments

  • Question
  • The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as


  • Options
  • A. event
  • B. free float
  • C. dummy
  • D. constant

  • Correct Answer
  • dummy 


  • Construction Management problems


    Search Results


    • 1. The salient feature of functional organisation is

    • Options
    • A. strict adherence to specifications
    • B. separation of planning and design part
    • C. each individual maintains functional efficiency
    • D. work is properly planned and distributed
    • E. all the above.
    • Discuss
    • 2. A construction schedule is prepared after collecting

    • Options
    • A. number of operations
    • B. output of labour
    • C. output of machinery
    • D. quantity of various items
    • E. all the above.
    • Discuss
    • 3. The Overall in-charge of an organisation at the site responsible for the execution of the works, is

    • Options
    • A. Executive Engineer
    • B. Engineer
    • C. Junior Engineer
    • D. Sub overseer
    • E. Assistant Engineer.
    • Discuss
    • 4. Pick up the PERT event from the following:

    • Options
    • A. Digging of foundation started
    • B. Digging of foundation completed
    • C. Laying of concrete started
    • D. Laying of concrete completed
    • E. All the above.
    • Discuss
    • 5. CPM is

    • Options
    • A. synthesising in concepts
    • B. is built of activities oriented programme
    • C. is based on time estimate
    • D. is used for repetitive works
    • E. all the above.
    • Discuss
    • 6. Which one of the following represents an activity

    • Options
    • A. excavation for foundation
    • B. curing of concrete
    • C. setting of question paper
    • D. preparation of breakfast
    • E. all the above.
    • Discuss
    • 7. The most popular type of organisation used for Civil Engineering Constructions, is

    • Options
    • A. line organisation
    • B. line and staff organisation
    • C. functional organisation
    • D. effective organisation.
    • Discuss
    • 8. Bar charts are suitable for

    • Options
    • A. minor works
    • B. major works
    • C. large projects
    • D. all the Above.
    • Discuss
    • 9. In the given figure, the network of a project represents

    • Options
    • A. activity of an excavation of a footing
    • B. activity of an excavation which starts at event No. 1 and ends at even No. 2
    • C. activity of excavation which takes 8 units of time
    • D. none of these.
    • Discuss
    • 10. Mile Stone charts were invented in the year of

    • Options
    • A. 1910
    • B. 1920
    • C. 1930
    • D. 1940
    • E. 1950
    • Discuss


    Comments

    There are no comments.

Enter a new Comment