CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Discussion
Home
‣
Civil Engineering
‣
Construction Management
Comments
Question
The main principle of an organisation, is
Options
A. unity of command
B. cohegency
C. effective control at all levels
D. delegation of authority
E. all the above.
Correct Answer
all the above.
Construction Management problems
Search Results
1. Construction team means
Options
A. an engineer
B. an architect
C. an owner
D. a contractor
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
2. The object of technical planning, is
Options
A. preparation of specifications
B. preparation of estimates
C. initiating the procurement action of resources
D. taking remedial action for likely bottleneck in the execution
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
3. Critical path lies along the activities having total float
Options
A. positive
B. negative
C. zero
D. same.
Show Answer
Scratch Pad
Discuss
Correct Answer: zero
4. Site order book is used for recording
Options
A. instructions by the executive engineers
B. construction measurements
C. issue of store equipments
D. names of the casual labour.
Show Answer
Scratch Pad
Discuss
Correct Answer: instructions by the executive engineers
5. Completion of an activity on CPM network diagram, is generally known
Options
A. Event
B. Node
C. Connector
D. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
6. Henry Gantt developed Bar charts for planning and scheduling of projects in
Options
A. 1880
B. 1900
C. 1920
D. 1940
E. 1950
Show Answer
Scratch Pad
Discuss
Correct Answer: 1900
7. An Executive Engineer may have powers upto
Options
A. Rs. 25,000
B. Rs. 50,000
C. Rs. 100,000
D. Rs. 200,000
E. Rs. 500,000
Show Answer
Scratch Pad
Discuss
Correct Answer: Rs. 25,000
8. CPM is
Options
A. synthesising in concepts
B. is built of activities oriented programme
C. is based on time estimate
D. is used for repetitive works
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
9. Pick up the PERT event from the following:
Options
A. Digging of foundation started
B. Digging of foundation completed
C. Laying of concrete started
D. Laying of concrete completed
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
10. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
Options
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer.
Show Answer
Scratch Pad
Discuss
Correct Answer: Engineer
Comments
There are no comments.
Enter a new Comment
Save
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering