  • Question
  • Critical path lies along the activities having total float


  • Options
  • A. positive
  • B. negative
  • C. zero
  • D. same.

  • Correct Answer
  • zero 


  • Construction Management problems


    Search Results


    • 1. Site order book is used for recording

    • Options
    • A. instructions by the executive engineers
    • B. construction measurements
    • C. issue of store equipments
    • D. names of the casual labour.
    • Discuss
    • 2. Completion of an activity on CPM network diagram, is generally known

    • Options
    • A. Event
    • B. Node
    • C. Connector
    • D. All the above.
    • Discuss
    • 3. The time which results in the leasi, possible construction cost of an activity, is known

    • Options
    • A. normal time
    • B. slow time
    • C. crash time
    • D. standard time.
    • Discuss
    • 4. Modular co-ordination of construction means proper

    • Options
    • A. planning
    • B. designing
    • C. execution
    • D. all the above.
    • Discuss
    • 5. Pick up the incorrect statement from the following:

    • Options
    • A. An activity of a project is denoted by an arrow on the net work
    • B. The tail of the arrow indicates the start of the activity
    • C. The head of the arrow indicates the end of the activity
    • D. The arrows are drawn to scale from left to right
    • E. Each activity consumes a given time.
    • Discuss
    • 6. The object of technical planning, is

    • Options
    • A. preparation of specifications
    • B. preparation of estimates
    • C. initiating the procurement action of resources
    • D. taking remedial action for likely bottleneck in the execution
    • E. all the above.
    • Discuss
    • 7. Construction team means

    • Options
    • A. an engineer
    • B. an architect
    • C. an owner
    • D. a contractor
    • E. all the above.
    • Discuss
    • 8. The main principle of an organisation, is

    • Options
    • A. unity of command
    • B. cohegency
    • C. effective control at all levels
    • D. delegation of authority
    • E. all the above.
    • Discuss
    • 9. Henry Gantt developed Bar charts for planning and scheduling of projects in

    • Options
    • A. 1880
    • B. 1900
    • C. 1920
    • D. 1940
    • E. 1950
    • Discuss
    • 10. An Executive Engineer may have powers upto

    • Options
    • A. Rs. 25,000
    • B. Rs. 50,000
    • C. Rs. 100,000
    • D. Rs. 200,000
    • E. Rs. 500,000
    • Discuss


    Comments

    There are no comments.

Enter a new Comment