  • The ratio of minimum hourly flow to the average flow of sewage is


  • Options
  • A. 1/4
  • B. 1/3
  • C. 1/2
  • D. 3/4

  • Correct Answer
  • 1/3 


  • Waste Water Engineering problems


    Search Results


    • 1. The detention time of a circular tank of diameter d and water depth H, for receiving the sewage Q per hour, is

    • Options
    • A.
    • B.
    • C.
    • D.
    • Discuss
    • 2. Chlorination of water is done for the removal of

    • Options
    • A. bacterias
    • B. suspended solids
    • C. sediments
    • D. hardness.
    • Discuss
    • 3. The width of a rectangular sewer is twice its depth while discharging 1.5 m/sec. The width of the sewer is

    • Options
    • A. 0.68 m
    • B. 0.88 m
    • C. 1.36 m
    • D. 1.76 m.
    • Discuss
    • 4. In R.C. sewer pipes, the percentage longitudinal reinforcement to the cross-sectional area of concrete is kept

    • Options
    • A. 10.0
    • B. 5.0
    • C. 2.0
    • D. 0.25
    • Discuss
    • 5. A sewer pipe contains 1 mm sand particles of specific gravity 2.65 and 5 mm organic particles of specific gravity 1.2, the minimum velocity required for removing the sewerage, is

    • Options
    • A. 0.30 m/sec
    • B. 0.35 m/sec
    • C. 0.40 m/sec
    • D. 0.45 m/sec
    • E. 0.50 m/sec.
    • Discuss
    • 6. Dilution method of disposing off sewage, is not preferred to

    • Options
    • A. when sewage is fresh
    • B. when diluting water has high dissolved oxygen content
    • C. when diluting water is used for water supply near the point of sewage disposed
    • D. when the diluting water is having flow currents
    • E. none of these.
    • Discuss
    • 7. An inverted siphon is designed generally for

    • Options
    • A. one pipe
    • B. two pipes
    • C. three pipes
    • D. four pipes.
    • Discuss
    • 8. The non-clog pump which permits solid matter to pass out with the liquid sewage, is

    • Options
    • A. centrifugal pump
    • B. reciprocating pump
    • C. pneumatic ejector
    • D. none of these.
    • Discuss
    • 9. Pick up the in-correct statement from the following :

    • Options
    • A. Manholes are provided in sewer pipes at suitable intervals
    • B. Catch basins are generally provided in sewers for carrying drainage discharge
    • C. Inlets are generally provided in all sewers
    • D. None of these.
    • Discuss
    • 10. Bio-chemical oxygen demand (BOD) for the first 20 days in generally referred to

    • Options
    • A. initial demand
    • B. first stage demand
    • C. carbonaceous demand
    • D. all of these.
    • Discuss